Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.

How can the project manager configure this relationship?

A.
Add a cross-project predecessor on the final milestone of Project 1.
Answers
A.
Add a cross-project predecessor on the final milestone of Project 1.
B.
Add a cross-project predecessor on Task 1 in Project 1.
Answers
B.
Add a cross-project predecessor on Task 1 in Project 1.
C.
Add a cross-project predecessor on the final milestone in Project 2.
Answers
C.
Add a cross-project predecessor on the final milestone in Project 2.
Suggested answer: C

Explanation:

In Workfront, cross-project predecessors allow dependencies between tasks across different projects. To ensure that Task 1 in Project 1 starts only after the final milestone of Project 2, the project manager must configure a cross-project predecessor linking the final milestone in Project 2 to Task 1 in Project 1. This establishes a dependency and aligns the timelines of the two projects.