Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.
How can the project manager configure this relationship?
A.
Add a cross-project predecessor on the final milestone of Project 1.
B.
Add a cross-project predecessor on Task 1 in Project 1.
C.
Add a cross-project predecessor on the final milestone in Project 2.
Your answer: