Question 35 - AD0-E903 discussion

Report
Export

A video designer is spending an excessive number of hours on a project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this project are necessary and suspects that the number of hours budgeted for the video designer's time on this project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this project so that the designer can still meet commitments on other assigned work.

Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this project vary from the Actual Hours spent on the project?

A.
Utilization
Answers
A.
Utilization
B.
Workload Balancer
Answers
B.
Workload Balancer
C.
Hours
Answers
C.
Hours
Suggested answer: B

Explanation:

The Workload Balancer in Workfront is used to compare planned hours against actual hours worked, providing a clear view of resource allocation and over-utilization. In this case, the project manager can use the Workload Balancer to demonstrate how the video designer's planned hours for the project differ from the actual hours spent. This helps the project manager make data-driven decisions about resource adjustments.