Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?

A.
Update the project status.
Answers
A.
Update the project status.
B.
Recalculate the project timeline.
Answers
B.
Recalculate the project timeline.
C.
Update the project baseline.
Answers
C.
Update the project baseline.
Suggested answer: B

Explanation:

In Adobe Workfront, to avoid sending unnecessary notifications when adjusting timelines, the Recalculate the project timeline option is used. This ensures that the timeline is updated appropriately based on the changes, but it prevents the system from sending notification alerts to the project team. Recalculation helps align task dependencies and timeline adjustments, preventing confusion among team members.