The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.
Which report grants the executive team this visibility?
A.
A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.
B.
A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.
C.
A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.