Which of the following should be the FIRST step m managing the impact of a recently discovered zero-day attack?

A.
Evaluating the likelihood of attack
A.
Evaluating the likelihood of attack
Answers
B.
Estimating potential damage
B.
Estimating potential damage
Answers
C.
Identifying vulnerable assets
C.
Identifying vulnerable assets
Answers
D.
Assessing the Impact of vulnerabilities
D.
Assessing the Impact of vulnerabilities
Answers
Suggested answer: C

Explanation:

The first step in managing the impact of a recently discovered zero-day attack is to identify vulnerable assets. A zero-day attack is a cyberattack that exploits a previously unknown or unpatched vulnerability in a software or system, before the vendor or developer has had time to fix it. Identifying vulnerable assets is crucial for managing the impact of a zero-day attack, because it helps to determine the scope and severity of the attack, prioritize the protection and mitigation measures, and isolate or quarantine the affected assets from further damage or compromise.The other options are not the first steps in managing the impact of a zero-day attack, because they either require more information about the vulnerable assets, or they are part of the subsequent steps of assessing, responding, or recovering from the attack.Reference:CISA Review Manual (Digital Version)1, Chapter 5, Section 5.2.4

Which of the following is me GREATE ST impact as a result of the ongoing deterioration of a detective control?

A.
Increased number of false negatives in security logs
A.
Increased number of false negatives in security logs
Answers
B.
Decreased effectiveness of roof cause analysis
B.
Decreased effectiveness of roof cause analysis
Answers
C.
Decreased overall recovery time
C.
Decreased overall recovery time
Answers
D.
Increased demand for storage space for logs
D.
Increased demand for storage space for logs
Answers
Suggested answer: A

Explanation:

The greatest impact as a result of the ongoing deterioration of a detective control is an increased number of false negatives in security logs. A detective control is a control that monitors and identifies any deviations or anomalies from the expected or normal behavior or performance of a system or process. A security log is a record of events or activities that occur within a system or network, such as user access, file changes, system errors, or security incidents. A false negative is a situation where a security log fails to detect or report an actual deviation or anomaly that has occurred, such as an unauthorized access, a malicious modification, or a security breach. An increased number of false negatives in security logs can have a significant impact on the organization's security posture and risk management, because it can prevent timely detection and response to security threats, compromise the accuracy and reliability of security monitoring and reporting, and undermine the accountability and auditability of user actions and transactions.The other options are not as impactful as an increased number of false negatives in security logs, because they either do not affect the detection capability of a detective control, or they have less severe consequences for security management.Reference:CISA Review Manual (Digital Version)1, Chapter 5, Section 5.2.1

An auditee disagrees with a recommendation for corrective action that appears in the draft engagement report. Which of the following is the IS auditor's BEST course of action when preparing the final report?

A.
Come to an agreement prior to issuing the final report.
A.
Come to an agreement prior to issuing the final report.
Answers
B.
Include the position supported by senior management in the final engagement report
B.
Include the position supported by senior management in the final engagement report
Answers
C.
Ensure the auditee's comments are included in the working papers
C.
Ensure the auditee's comments are included in the working papers
Answers
D.
Exclude the disputed recommendation from the final engagement report
D.
Exclude the disputed recommendation from the final engagement report
Answers
Suggested answer: B

Explanation:

The IS auditor's best course of action when preparing the final report is to include the position supported by senior management in the final engagement report. The IS auditor should communicate the audit findings and recommendations to senior management and obtain their feedback and approval before issuing the final report. If there is a disagreement between the auditee and the IS auditor regarding a recommendation for corrective action, the IS auditor should present both sides of the argument and the supporting evidence, and seek senior management's opinion and decision. The IS auditor should respect and follow senior management's position, and include it in the final engagement report, along with the auditee's comments if applicable.The other options are not the best course of action, because they either do not resolve the disagreement, do not reflect senior management's authority, or do not report the audit results accurately and completely.Reference:CISA Review Manual (Digital Version)1, Chapter 2, Section 2.2.5

Which of the following would provide the BEST evidence of an IT strategy corrections effectiveness?

A.
The minutes from the IT strategy committee meetings
A.
The minutes from the IT strategy committee meetings
Answers
B.
Synchronization of IT activities with corporate objectives
B.
Synchronization of IT activities with corporate objectives
Answers
C.
The IT strategy committee charier
C.
The IT strategy committee charier
Answers
D.
Business unit satisfaction survey results
D.
Business unit satisfaction survey results
Answers
Suggested answer: B

Explanation:

The best evidence of an IT strategy correction's effectiveness is the synchronization of IT activities with corporate objectives. The IT strategy correction is a process of reviewing and adjusting the IT strategy to ensure that it aligns with and supports the corporate strategy and objectives. The synchronization of IT activities with corporate objectives means that the IT activities are consistent with and contribute to the achievement of the corporate goals and vision. The IS auditor can measure and evaluate the IT strategy correction's effectiveness by comparing the IT activities with the corporate objectives, and assessing whether they are aligned, integrated, and coordinated.The other options are not as good evidence of an IT strategy correction's effectiveness, because they either do not reflect the alignment of IT and business, or they are inputs or outputs of the IT strategy correction process rather than outcomes or results.Reference:CISA Review Manual (Digital Version)1, Chapter 1, Section 1.2.1

An IT balanced scorecard is PRIMARILY used for:

A.
evaluating the IT project portfolio
A.
evaluating the IT project portfolio
Answers
B.
measuring IT strategic performance
B.
measuring IT strategic performance
Answers
C.
allocating IT budget and resources
C.
allocating IT budget and resources
Answers
D.
monitoring risk in lT-related processes
D.
monitoring risk in lT-related processes
Answers
Suggested answer: B

Explanation:

An IT balanced scorecard is primarily used for measuring IT strategic performance. An IT balanced scorecard is a framework that translates the IT strategy into measurable objectives, indicators, targets, and initiatives across four perspectives: financial, customer, internal process, and learning and growth. An IT balanced scorecard helps to monitor and evaluate how well the IT function is delivering value to the organization, achieving its strategic goals, and improving its capabilities and competencies.The other options are not the primary uses of an IT balanced scorecard, because they either focus on specific aspects of IT rather than the overall performance, or they are not directly related to the IT strategy.Reference:CISA Review Manual (Digital Version)1, Chapter 1, Section 1.2.3

An IS auditor notes that not all security tests were completed for an online sales system recently promoted to production. Which of the following is the auditor's BEST course of action?

A.
Determine exposure to the business
A.
Determine exposure to the business
Answers
B.
Adjust future testing activities accordingly
B.
Adjust future testing activities accordingly
Answers
C.
Increase monitoring for security incidents
C.
Increase monitoring for security incidents
Answers
D.
Hire a third party to perform security testing
D.
Hire a third party to perform security testing
Answers
Suggested answer: A

Explanation:

The IS auditor's best course of action when reviewing the use of an outsourcer for disposal of storage media is to determine exposure to the business. Storage media, such as hard disks, tapes, flash drives, or CDs, may contain sensitive or confidential information that needs to be protected from unauthorized access, disclosure, or misuse. The IS auditor should verify that the outsourcer has a process that appropriately sanitizes the media before disposal, such as wiping, degaussing, shredding, or incinerating, and that the process is effective and compliant with the organization's policies and standards. The IS auditor should also assess the potential impact and risk to the business if the storage media is not properly sanitized or disposed of, such as data breaches, reputational damage, legal or regulatory penalties, or loss of competitive advantage.The other options are not the best course of action, because they either do not address the root cause of the problem, or they are reactive rather than proactive measures.Reference:CISA Review Manual (Digital Version)1, Chapter 5, Section 5.2.7

Which of the following is MOST important for an IS auditor to verify when reviewing the use of an outsourcer for disposal of storage media?

A.
The vendor's process appropriately sanitizes the media before disposal
A.
The vendor's process appropriately sanitizes the media before disposal
Answers
B.
The contract includes issuance of a certificate of destruction by the vendor
B.
The contract includes issuance of a certificate of destruction by the vendor
Answers
C.
The vendor has not experienced security incidents in the past.
C.
The vendor has not experienced security incidents in the past.
Answers
D.
The disposal transportation vehicle is fully secure
D.
The disposal transportation vehicle is fully secure
Answers
Suggested answer: A

Explanation:

The most important thing for an IS auditor to verify when reviewing the use of an outsourcer for disposal of storage media is that the vendor's process appropriately sanitizes the media before disposal. As explained in the previous question, storage media may contain sensitive or confidential information that needs to be protected from unauthorized access, disclosure, or misuse. The IS auditor should verify that the vendor has a process that appropriately sanitizes the media before disposal, such as wiping, degaussing, shredding, or incinerating, and that the process is effective and compliant with the organization's policies and standards.The other options are not as important as verifying the vendor's process, because they either do not ensure the security and privacy of the information on the media, or they are secondary to the vendor's process.Reference:CISA Review Manual (Digital Version)1, Chapter 5, Section 5.2.7

An IS department is evaluated monthly on its cost-revenue ratio user satisfaction rate, and computer downtime This is BEST zed as an application of.

A.
risk framework
A.
risk framework
Answers
B.
balanced scorecard
B.
balanced scorecard
Answers
C.
value chain analysis
C.
value chain analysis
Answers
D.
control self-assessment (CSA)
D.
control self-assessment (CSA)
Answers
Suggested answer: B

Explanation:

. A balanced scorecard is a framework that translates the IT strategy into measurable objectives, indicators, targets, and initiatives across four perspectives: financial, customer, internal process, and learning and growth. A balanced scorecard helps to monitor and evaluate how well the IT function is delivering value to the organization, achieving its strategic goals, and improving its capabilities and competencies. The other options are not the primary uses of a balanced scorecard, because they either focus on specific aspects of IT rather than the overall performance, or they are not directly related to the IT strategy.

Which of the following is the PRIMARY reason for an IS audit manager to review the work performed by a senior IS auditor prior to presentation of a report?

A.
To ensure the conclusions are adequately supported
A.
To ensure the conclusions are adequately supported
Answers
B.
To ensure adequate sampling methods were used during fieldwork
B.
To ensure adequate sampling methods were used during fieldwork
Answers
C.
To ensure the work is properly documented and filed
C.
To ensure the work is properly documented and filed
Answers
D.
To ensure the work is conducted according to industry standards
D.
To ensure the work is conducted according to industry standards
Answers
Suggested answer: A

Explanation:

The primary reason for an IS audit manager to review the work performed by a senior IS auditor prior to presentation of a report is to ensure the conclusions are adequately supported. The IS audit manager is responsible for overseeing and supervising the audit process, ensuring the quality and consistency of the audit work, and approving the audit report and recommendations. The IS audit manager should review the work performed by the senior IS auditor to verify that the audit objectives, scope, and criteria have been met, that the audit evidence is sufficient, reliable, and relevant, and that the audit conclusions are logical, objective, and based on the audit evidence. The IS audit manager should also ensure that the audit report is clear, concise, accurate, and complete, and that it communicates the audit findings, conclusions, and recommendations effectively to the intended audience.The other options are not the primary reason for an IS audit manager to review the work performed by a senior IS auditor prior to presentation of a report, because they either relate to specific aspects or stages of the audit work rather than the overall outcome, or they are part of the senior IS auditor's responsibility rather than the IS audit manager's.Reference:CISA Review Manual (Digital Version)1, Chapter 2, Section 2.2.5

Which of following is MOST important to determine when conducting a post-implementation review?

A.
Whether the solution architecture compiles with IT standards
A.
Whether the solution architecture compiles with IT standards
Answers
B.
Whether success criteria have been achieved
B.
Whether success criteria have been achieved
Answers
C.
Whether the project has been delivered within the approved budget
C.
Whether the project has been delivered within the approved budget
Answers
D.
Whether lessons teamed have been documented
D.
Whether lessons teamed have been documented
Answers
Suggested answer: B

Explanation:

The most important thing to determine when conducting a post-implementation review is whether success criteria have been achieved. A post-implementation review is a process of evaluating the results and outcomes of a project or initiative after it has been completed and implemented. The success criteria are the measurable indicators that define what constitutes a successful project or initiative in terms of its objectives, benefits, quality, performance, and stakeholder satisfaction. The IS auditor should verify whether the success criteria have been achieved by comparing the actual results and outcomes with the expected or planned ones, and by assessing whether they meet or exceed the expectations and requirements of the stakeholders. The IS auditor should also identify any gaps, issues, or risks that may affect the sustainability or scalability of the project or initiative, and provide recommendations for improvement or remediation.The other options are not as important as determining whether success criteria have been achieved when conducting a post-implementation review, because they either focus on specific aspects or components of the project or initiative rather than the overall value proposition, or they are part of the pre-implementation or implementation phases rather than the post-implementation phase.Reference:CISA Review Manual (Digital Version)1, Chapter 4, Section 4.2.3