DRAG DROP

What is the correct order in which the XtremlO X1 cluster components should be powered on for the first time?

Question 51
Correct answer: Question 51

Explanation:

PDU (Power Distribution Unit)

BBUs (Battery Backup Units)

XMS (XtremIO Management Server)

Storage Controllers


Which port should SC1-IB1 be connected to in a single X-Brick XtremIO X2?

A.
IBSW1-P01
A.
IBSW1-P01
Answers
B.
SC2-IB2
B.
SC2-IB2
Answers
C.
SC2-IB1
C.
SC2-IB1
Answers
D.
IBSW2-P01
D.
IBSW2-P01
Answers
Suggested answer: A

Explanation:

In a single X-Brick XtremIO X2 configuration, the port SC1-IB1 should be connected to IBSW1-P01. This connection ensures proper communication and data flow between the storage controller and the InfiniBand switch, which is critical for system performance and redundancy.

Which port is used to connect to the Storage Controller (SC) to service an XtremIO X2 with the Technician Advisor tool?

A.
Dedicated serial port on the back on the SC
A.
Dedicated serial port on the back on the SC
Answers
B.
Dedicated USB port on the front of the SC
B.
Dedicated USB port on the front of the SC
Answers
C.
Dedicated USB port on the back of the SC
C.
Dedicated USB port on the back of the SC
Answers
D.
Dedicated Management port on the back of the SC
D.
Dedicated Management port on the back of the SC
Answers
Suggested answer: D

Explanation:

To service an XtremIO X2 with the Technician Advisor tool, the connection is made through the dedicated Management port located on the back of the Storage Controller (SC). This port is specifically designed for management tasks and allows service technicians to access the system for diagnostics and configuration using the Technician Advisor tool1.

The process typically involves:

Locating the dedicated Management port on the back of the SC.

Connecting a compatible cable from the technician's device to the Management port.

Using the Technician Advisor tool to perform the necessary service tasks.

This information is outlined in the Official Dell XtremIO Maintenance Achievement document, which provides detailed instructions for servicing and maintaining XtremIO X2 storage systems1.

=========================

A multi X-Brick XtremlO X1 cluster is being installed. How many BBU connections, and of which type, are required per X-Brick?

A.
2 BBUs providing protective power to the Storage Controllers 1 BBU COM port connected to the bottom Storage Controller
A.
2 BBUs providing protective power to the Storage Controllers 1 BBU COM port connected to the bottom Storage Controller
Answers
B.
1 BBU providing protective power to the bottom Storage Controller 2 BBU COM ports; one connected to each Storage Controller
B.
1 BBU providing protective power to the bottom Storage Controller 2 BBU COM ports; one connected to each Storage Controller
Answers
C.
1 BBU providing protective power to the Storage Controllers 2 BBU COM ports; one connected to each Storage Controller
C.
1 BBU providing protective power to the Storage Controllers 2 BBU COM ports; one connected to each Storage Controller
Answers
D.
2 BBUs providing protective power to X-Brick 1 and 2 Storage Controllers only 4 BBU COM ports connected to each Storage Controller
D.
2 BBUs providing protective power to X-Brick 1 and 2 Storage Controllers only 4 BBU COM ports connected to each Storage Controller
Answers
Suggested answer: C

Explanation:

For a multi X-Brick XtremIO X1 cluster, each X-Brick requires one Battery Backup Unit (BBU) that provides protective power to both Storage Controllers within the X-Brick. Additionally, there are two BBU COM (communication) ports required, with one connected to each Storage Controller. This configuration ensures that in the event of a power failure, the BBU can maintain power to the Storage Controllers, allowing them to safely shut down and protect data integrity1.

The installation process would typically involve:

Installing the BBU in the designated slot within the X-Brick.

Connecting the BBU power cable to the power supply of both Storage Controllers.

Connecting a BBU COM port to each Storage Controller for communication and monitoring purposes.

This setup is crucial for maintaining the high availability and data protection standards that XtremIO systems are known for1.

=========================

DRAG DROP

What is the correct sequence of steps to power up an XtremlO X1 cluster after an emergency shutdown?

Question 55
Correct answer: Question 55

Explanation:

Determine the cause of the shutdown

Power up the Battery Backup Units

Power up the XMS

Power up the Storage Controllers

Start the cluster