Which of the following is NOT one of the benefits of reducing work-in-progress?

A.
Allows you to multi-task between many high priority items
A.
Allows you to multi-task between many high priority items
Answers
B.
Reduces the lead time
B.
Reduces the lead time
Answers
C.
Creates a greater incentive to prioritize
C.
Creates a greater incentive to prioritize
Answers
D.
Create focus
D.
Create focus
Answers
Suggested answer: A

The principle "Organize around products/services" means that:

A.
Customers should be asked to pick from the available products or services
A.
Customers should be asked to pick from the available products or services
Answers
B.
Building dedicated cross-functional teams focused on customer offerings
B.
Building dedicated cross-functional teams focused on customer offerings
Answers
C.
Project teams are best equipped to deliver products
C.
Project teams are best equipped to deliver products
Answers
Suggested answer: B

True or False: The Control process blade is also responsible for ensuring regulatory compliance

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: B

True or False: A project that follows a Scrum or Agile life-cycle still needs the Inception, Construction or Transition phases.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: A

The primary advantage of breaking a project into phases is that:

A.
It makes the transition from waterfall to agile easier
A.
It makes the transition from waterfall to agile easier
Answers
B.
You can bring in new teams in each phase depending upon the skills needed for it
B.
You can bring in new teams in each phase depending upon the skills needed for it
Answers
C.
It allows the team to perform mini-waterfalls in each phase
C.
It allows the team to perform mini-waterfalls in each phase
Answers
D.
It enables teams to focus on critical themes and ease of governance
D.
It enables teams to focus on critical themes and ease of governance
Answers
Suggested answer: D

If the frequency of changes to requirements is very high (almost daily), which of the following lifecycle models might make most sense?

A.
Scrum
A.
Scrum
Answers
B.
Lean
B.
Lean
Answers
C.
Continuous delivery Agile
C.
Continuous delivery Agile
Answers
D.
Agile
D.
Agile
Answers
Suggested answer: B

According to the DA manifesto, Transparency is valued over false predictability. This means that:

A.
It is pointless trying to be predictable
A.
It is pointless trying to be predictable
Answers
B.
Being open is better than pretending that we can predict the future
B.
Being open is better than pretending that we can predict the future
Answers
C.
Stakeholders don't really need to know about the goals
C.
Stakeholders don't really need to know about the goals
Answers
D.
Predictability is achieved only through transparency
D.
Predictability is achieved only through transparency
Answers
Suggested answer: B

Which of the following is a disadvantage of having a feature team as opposed to component teams?

A.
One team delivers a feature from top to bottom
A.
One team delivers a feature from top to bottom
Answers
B.
There are lesser hand-offs across teams
B.
There are lesser hand-offs across teams
Answers
C.
Require cross-functional team members
C.
Require cross-functional team members
Answers
D.
There is a temptation to build everything from scratch
D.
There is a temptation to build everything from scratch
Answers
Suggested answer: D

Which of the following best expresses the meaning of a Value Stream Map?

A.
The physical movement of parts or people in a process
A.
The physical movement of parts or people in a process
Answers
B.
A pictorial representation of the organization's product or offerings
B.
A pictorial representation of the organization's product or offerings
Answers
C.
A method used to quantify the return on investment for an organization
C.
A method used to quantify the return on investment for an organization
Answers
D.
A series of steps that are carried out to deliver something of value to the customer
D.
A series of steps that are carried out to deliver something of value to the customer
Answers
Suggested answer: D

Which of the following may not help in improving predictability?

A.
Estimate in hours instead of points
A.
Estimate in hours instead of points
Answers
B.
Reduce technical debt
B.
Reduce technical debt
Answers
C.
Reduce feedback cycles
C.
Reduce feedback cycles
Answers
D.
Respect WIP limits
D.
Respect WIP limits
Answers
E.
Adopt a test-first approach
E.
Adopt a test-first approach
Answers
Suggested answer: A