Question 1
For FusionModule2000, depending on different layout position, batteries can be deployed in the smart module or out of the smart module.
Question 2
After all historical alarms of the NetCol5000-A are deleted, the deletion operation is not logged.
Question 3
Commissioning NetCol5000-C drainage devices, after lifting the high float for 5 seconds, two water pumps start working, and the drain abnormal alarm is generated.
Question 4
The UPS can generate large leakage currents. A circuit breaker equipped with a residual current device (RCD) is not recommended. If leakage protection is required, consider the leakage current of the UPS and downstream devices.
Question 5
As the altitude increases, the air density decreases, and the heat exchange capability of the air in a unit volume decreases. In this case, NetCol8000-E220 works with derating.
Question 6
When connecting chilled water pipes for the NetCol8000-C, fill water and preserve pressure 8 hours after the conversion adapter is connected.
Question 7
The UPS5000-E-200K works in normal mode. If two ECMs are faulty, how does the UPS work?
Question 8
Refer to the exhibit.
Question 9
When installing a water-cooled module, what is the minimum distance between the module and the wall?
Question 10
On the ECC800-Pro WebUI, which of the following is the first-level menu of the NMS Application?
Question