Which of the following is a standard component in the FusionModule800 typical configuration?
When will the bypass module of Huawei integrated UPS to start to work?
The power system of a UPS2000-G-15K at a site is three-phase input and single-phase output. After installation, it is found that the mains and bypass inputs are three-phase, the output is single-phase, and the mains and bypass inputs share a power source. Which of the following statements are true about the UPS wiring mode?
During the installation of an air conditioner system, which of the following statements are correct about the draining impurities from the refrigerant pipe?
In the FusionModule800 grounding solution, each cabinet is connected to the ground bar of the data center.
During filling refrigerant for NetCol5000-A, there is no need to put the refrigerant steel cylinder upside down on balance.
The ECC800-Pro is the core component for FusionModule2000 local management. Southbound components can be using the PoE bus.
In the water-side free cooling solution, cold water cannot be transported directly from the cooling tower to chilled conditioner?
If the UPS5000-E is overloaded in normal mode, it transfers to bypass mode immediately. The bypass supplies power to loads to protect the UPS.