Question 21

You need to plan scheduling for Customer1's order of unscented solution.
What are two possible ways to achieve the goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Schedule production based on the availability of raw material.
Split and plan operations in detail for each of the resources.
Schedule productions based on the capacity of the resources.
Run master planning with a specific time fence.
Plan scheduling of the production at the resource group level.
Question 22

DRAG DROP
You need to create the new summer limited edition bicycle in Dynamics 365 in preparation for taking orders.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
https://docs.microsoft.com/en-us/dynamics365/supply-chain/pim/dimension-based-product-configuration
Explanation:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/pim/dimension-based-product-configuration
Question 23

You need to create the production orders for standard model bicycles.
Which method should you use?
Sales order line
Master planning execution
Supply schedule form
Released item
All production orders form
Explanation:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/supply-schedule
Question 24

You need to configure the bicycles' production resource.
Which option should you use?
Exclusive capacity set to yes and enter a Batch capacity.
Exclusive capacity set to no and infinite capacity.
Exclusive capacity set to yes and infinite capacity.
Exclusive capacity set to no and enter a Batch capacity.
Explanation:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/operations-resources
Question 25

You need to determine the sales price for a new limited-edition bicycle for the summer season.
What should you do?
Run inventory close for the BOM items for the limited-edition bicycle.
Create the production order for the limited-edition bicycle and click estimate.
Run the category price rules for the limited-edition bicycle using a cost-plus calculation.
Run the pricing simulator for the limited-edition bicycle for a quantity of one.
Explanation:
Fabrikam, Inc. Is a discrete manufacturer of outdoor patio furniture. The company originated as a sole owner working from a home garage, then moved into a commercial storage space, and later into a full manufacturing facility. The company operates as two operating legal entities, one in the United States and the other in Mexico.
As the company grew, the existing software systems failed to grow with it. This meant that financial reporting was managed in an outdated accounting system; raw materials planning, production, and inventory control were managed in another system; and cost calculations were tracked in multiple spreadsheets managed by analysts.
Question 26

HOTSPOT
You need to resolve the issue for UserF.
What should you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Question 27

You need to resolve the issue for UserC.
Which two options should you configure? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Best before period in days
Best advice period in days
Backward tracing
Forward tracing
Shelf life period in days
Question 28

HOTSPOT
You need to resolve the issue for UserG.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Question 29

You need to configure the system to track the cost and delivery performance of VendorZ.
Which two actions should you perform? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Add an activity to the production route for deliveries.
Create a service product and set Stocked product - Yes.
Add an activity to the production flow for deliveries.
Create a service product and set Stocked product = No.
Question 30

You need to resolve the issue for UserB.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Set up configuration and weight for partial visibility.
Create a product master with predefined variants for ounces and boxes.
Set up configuration and weight for full visibility.
Create a catch weight item.