HOTSPOT
A bicycle manufacturing company is implementing Dynamics 365 Supply Chain Management.
The warehouse must pick and stage parts other than paint for bicycle assembly. Paint is at the production station.
You need to configure the reservations for production.
What should you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
A manufacturer is implementing Dynamics 365 Supply Chain Management with warehouse management processes (WMS).
Warehouse workers use hand-held devices to pick and stage batch-tracked products for production. The warehouse manager requires that products are removed from on-hand inventory and consumed when they are picked and staged for production.
You need to remove the products from on-hand inventory.
What should you configure?
mobile device menu item, start production order
flushing principle, available al location
flushing principle, start
manufacturing execution, job card device
DRAG DROP
A manufacturer is implementing Dynamics 365 Supply Chain Management to create blends of oil and industrial lubricant.
The manufacturer requires detailed documentation for the production order process before manufacturing begins for the products. The shop floor must review, approve, and anticipate all production runs. Before production starts, the manufacturer wants to ensure that the order can be completed by a certain timeframe based on capacity.
You need to define the production life cycle stages.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
A company uses Dynamics 365 Supply Chain Management.
The marketing group needs to be able to view a manufacturer's suggested retail price (MSRP) for a new bill of materials (BOM) item when the cost of the BOM item is calculated.
You need to configure the functionality.
What should you do?
Set the sales price model field on the calculation group to item sales price.
Use the category price rules to generate a trade agreement with the sales price.
Add a profit setting percentage to a calculation group.
Add a profit setting percentage to the released BOM product.
Add a profit setting percentage to a cost group.
DRAG DROP
A company overstates on-hand raw materials due to the time it takes to post raw materials as consumed when production orders are processed.
All items used to manufacture finished goods must be consumed when a finished good is reported as finished. You must not change all bill of materials lines to use the option of flushing principal.
You need to ensure that all production orders consume raw materials at Report as finished.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
In the Production order status section of Production control, select Start
In the Picking list journal, select Always in the Automatic BOM consumption
In the Production order status section of Production control, select Report as finished
Select Make default for all users
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/production-parameters-manufacturing-execution
A company produces paints and assembles bicycle frames.
You must account for paint drying time before assembly operations can begin.
You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents pad of the solution.
NOTE: Each correct selection is worth one point.
Build capabilities for each resource related to color.
Enter a value in the queue time after field for the painting operation.
Enter a value in the transit time on the painting operation.
Make a resource group for each size and color and assign that group to the operation.
Enter a value in the queue time before field for the assembly operation.
DRAG DROP
A company plans to account for indirect costs related to materials used to manufacture products.
The items used to manufacture products have surcharge rates that depend on the type of product being used.
You need to set up the costing sheet to include surcharges for specific items.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
DRAG DROP
A manufacturing company is implementing Dynamics 365 Supply Cham Management.
Bill of materials (BOMs) must be calculated using standard cost principles.
Miscellaneous charges must be included in the unit cost price. The explosion mode must arways be enforced as single level.
You need to configure the system to meet the requirements.
Which configuration should you enable for each requirement? To answer, drag the appropriate configurations to the correct requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
A company produces pipe at certain fixed lengths.
The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?
Build capability related to length and assign to the appropriate resources.
Configure the Data/Hour option on the Capacity unit field on the resource.
Create a resource for each length.
Create a resource group for each length.
HOTSPOT
A manufacturer uses Dynamics 365 Supply Chain Management to create bicycle parts as a configure-to-order configuration. All bicycle parts are sourced from external sources and assembled in the manufacturing facility.
The manufacturer plans to expand its capabilities to create custom bicycles parts in an engineer-to-order model. All bicycle parts will be created in the manufacturing facility. The custom bicycle parts must be omitted from any master planning process.
You need to describe the concepts for the requirements.
Which concepts should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Question