When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?

A.
It should be used when planning at the delivery level
A.
It should be used when planning at the delivery level
Answers
B.
It should be used when planning at the project level
B.
It should be used when planning at the project level
Answers
C.
It should be used when controlling the quality of the products delivered
C.
It should be used when controlling the quality of the products delivered
Answers
D.
It should be used when monitoring the amount of products delivered
D.
It should be used when monitoring the amount of products delivered
Answers
Suggested answer: B

Which statement about the ‘accept that the customer doesn't need everything’ target is CORRECT?

A.
It is achieved by testing only a few features to deliver on time
A.
It is achieved by testing only a few features to deliver on time
Answers
B.
It is achieved by ensuring that the operational product has complete documentation
B.
It is achieved by ensuring that the operational product has complete documentation
Answers
C.
It is based on the concept that people generally use a limited number of product features
C.
It is based on the concept that people generally use a limited number of product features
Answers
D.
It enables a more accurate final product to be produced
D.
It enables a more accurate final product to be produced
Answers
Suggested answer: C

When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

A.
How to adapt the PRINCE2 management products
A.
How to adapt the PRINCE2 management products
Answers
B.
How to select which Agile framework should be favoured
B.
How to select which Agile framework should be favoured
Answers
C.
How to decide whether PRINCE2 is appropriate
C.
How to decide whether PRINCE2 is appropriate
Answers
D.
How to calculate the project budget and cost tolerance
D.
How to calculate the project budget and cost tolerance
Answers
Suggested answer: A

What does velocity typically measure?

A.
Work packages completed by the team
A.
Work packages completed by the team
Answers
B.
The rate of progress the team is making
B.
The rate of progress the team is making
Answers
C.
The number of timeboxes completed
C.
The number of timeboxes completed
Answers
D.
The speed that a minimum viable product is created
D.
The speed that a minimum viable product is created
Answers
Suggested answer: B

Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?

1) It should be replaced by the project manager attending a daily stand-up.

2) It should be displayed in the form of an information radiator in a team room.

3) It should be produced when the amount to be delivered will result in tolerance being exceeded.

4) It should be produced in a product backlog in the form of prioritized user stories.

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: B

When creating the project product description, how should the purpose of the project product be defined?

A.
As an opportunity
A.
As an opportunity
Answers
B.
As a vision
B.
As a vision
Answers
C.
As an outcome
C.
As an outcome
Answers
D.
As a goal
D.
As a goal
Answers
Suggested answer: C

Which is a purpose of the plans theme?

A.
To identify any deviations from the project’s objectives
A.
To identify any deviations from the project’s objectives
Answers
B.
To control any approved changes to the baseline
B.
To control any approved changes to the baseline
Answers
C.
To monitor actual achievements against those planned
C.
To monitor actual achievements against those planned
Answers
D.
To communicate the approach for delivering products
D.
To communicate the approach for delivering products
Answers
Suggested answer: D

Which should be an objective of a retrospective?

A.
To identify many process improvements and implement them
A.
To identify many process improvements and implement them
Answers
B.
To identify key process improvements to implement in the next sprint
B.
To identify key process improvements to implement in the next sprint
Answers
C.
To encourage the team to bond by allowing social activities to take place
C.
To encourage the team to bond by allowing social activities to take place
Answers
D.
To focus on objective learning rather than subjective feelings and emotions
D.
To focus on objective learning rather than subjective feelings and emotions
Answers
Suggested answer: B

What is typically displayed on a board to show progress to people working on a project?

A.
Agilometer assessment
A.
Agilometer assessment
Answers
B.
Product backlog
B.
Product backlog
Answers
C.
Information radiator
C.
Information radiator
Answers
D.
User story
D.
User story
Answers
Suggested answer: C

How is the ‘learn from experience’ principle applied in an agile context?

A.
By ensuring control through lots of short stages during innovative projects
A.
By ensuring control through lots of short stages during innovative projects
Answers
B.
By using the Agilometer to assess risks associated with the agile way of working
B.
By using the Agilometer to assess risks associated with the agile way of working
Answers
C.
By continual customer involvement to obtain feedback during the project
C.
By continual customer involvement to obtain feedback during the project
Answers
D.
By prioritizing quality criteria to focus the project on the delivery of value
D.
By prioritizing quality criteria to focus the project on the delivery of value
Answers
Suggested answer: C