PRINCE2 PRINCE2 Agile Foundation Practice Test - Questions Answers, Page 6
List of questions
Related questions
When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?
Which statement about the ‘accept that the customer doesn't need everything’ target is CORRECT?
When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?
What does velocity typically measure?
Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?
1) It should be replaced by the project manager attending a daily stand-up.
2) It should be displayed in the form of an information radiator in a team room.
3) It should be produced when the amount to be delivered will result in tolerance being exceeded.
4) It should be produced in a product backlog in the form of prioritized user stories.
When creating the project product description, how should the purpose of the project product be defined?
Which is a purpose of the plans theme?
Which should be an objective of a retrospective?
What is typically displayed on a board to show progress to people working on a project?
How is the ‘learn from experience’ principle applied in an agile context?
Question