Question 51

Report Export Collapse

When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?

It should be used when planning at the delivery level
It should be used when planning at the delivery level
It should be used when planning at the project level
It should be used when planning at the project level
It should be used when controlling the quality of the products delivered
It should be used when controlling the quality of the products delivered
It should be used when monitoring the amount of products delivered
It should be used when monitoring the amount of products delivered
Suggested answer: B
asked 23/09/2024
Bryan Smith
45 questions

Question 52

Report Export Collapse

Which statement about the ‘accept that the customer doesn't need everything’ target is CORRECT?

It is achieved by testing only a few features to deliver on time
It is achieved by testing only a few features to deliver on time
It is achieved by ensuring that the operational product has complete documentation
It is achieved by ensuring that the operational product has complete documentation
It is based on the concept that people generally use a limited number of product features
It is based on the concept that people generally use a limited number of product features
It enables a more accurate final product to be produced
It enables a more accurate final product to be produced
Suggested answer: C
asked 23/09/2024
Eduardo Cunha
36 questions

Question 53

Report Export Collapse

When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

How to adapt the PRINCE2 management products
How to adapt the PRINCE2 management products
How to select which Agile framework should be favoured
How to select which Agile framework should be favoured
How to decide whether PRINCE2 is appropriate
How to decide whether PRINCE2 is appropriate
How to calculate the project budget and cost tolerance
How to calculate the project budget and cost tolerance
Suggested answer: A
asked 23/09/2024
Minh Phan
33 questions

Question 54

Report Export Collapse

What does velocity typically measure?

Work packages completed by the team
Work packages completed by the team
The rate of progress the team is making
The rate of progress the team is making
The number of timeboxes completed
The number of timeboxes completed
The speed that a minimum viable product is created
The speed that a minimum viable product is created
Suggested answer: B
asked 23/09/2024
Aaron Case
49 questions

Question 55

Report Export Collapse

Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?

1) It should be replaced by the project manager attending a daily stand-up.

2) It should be displayed in the form of an information radiator in a team room.

3) It should be produced when the amount to be delivered will result in tolerance being exceeded.

4) It should be produced in a product backlog in the form of prioritized user stories.

Become a Premium Member for full access
  Unlock Premium Member

Question 56

Report Export Collapse

When creating the project product description, how should the purpose of the project product be defined?

Become a Premium Member for full access
  Unlock Premium Member

Question 57

Report Export Collapse

Which is a purpose of the plans theme?

Become a Premium Member for full access
  Unlock Premium Member

Question 58

Report Export Collapse

Which should be an objective of a retrospective?

Become a Premium Member for full access
  Unlock Premium Member

Question 59

Report Export Collapse

What is typically displayed on a board to show progress to people working on a project?

Become a Premium Member for full access
  Unlock Premium Member

Question 60

Report Export Collapse

How is the ‘learn from experience’ principle applied in an agile context?