Which describes the Scrum Master role in Scrum?

A.
It is authorized to run the project on a day-to-day basis on behalf of the project board
A.
It is authorized to run the project on a day-to-day basis on behalf of the project board
Answers
B.
It is responsible for ensuring that product backlog items are clearly expressed on the product backlog
B.
It is responsible for ensuring that product backlog items are clearly expressed on the product backlog
Answers
C.
It is empowered to organize and manage its own work to create a valuable, useful increment every sprint
C.
It is empowered to organize and manage its own work to create a valuable, useful increment every sprint
Answers
D.
It is servant-leadership to help everyone change their interactions to maximize the value created by the team
D.
It is servant-leadership to help everyone change their interactions to maximize the value created by the team
Answers
Suggested answer: B

Which statement about the ‘embrace change’ target is CORRECT?

A.
It re-establishes team dynamics when a new member joins the team
A.
It re-establishes team dynamics when a new member joins the team
Answers
B.
It trades user stories for those of a similar size
B.
It trades user stories for those of a similar size
Answers
C.
It results in the late delivery of the minimum viable product
C.
It results in the late delivery of the minimum viable product
Answers
D.
It degrades the performance of the features that are delivered
D.
It degrades the performance of the features that are delivered
Answers
Suggested answer: D

Which statement defines a PRINCE2 principle?

A.
A PRINCE2 project defines its quality management approach
A.
A PRINCE2 project defines its quality management approach
Answers
B.
A PRINCE2 project is monitored and controlled on a stage-by-stage basis
B.
A PRINCE2 project is monitored and controlled on a stage-by-stage basis
Answers
C.
A PRINCE2 project ensures a consistent approach to risk management
C.
A PRINCE2 project ensures a consistent approach to risk management
Answers
D.
A PRINCE2 project is tailored to suit the competitor’s environment
D.
A PRINCE2 project is tailored to suit the competitor’s environment
Answers
Suggested answer: B

Which is the BEST method of communication to gather feedback?

A.
Receiving emailed diagrams to encourage discussion
A.
Receiving emailed diagrams to encourage discussion
Answers
B.
Conducting online surveys to obtain a range of opinions
B.
Conducting online surveys to obtain a range of opinions
Answers
C.
Meeting face-to-face to encourage an exchange of views
C.
Meeting face-to-face to encourage an exchange of views
Answers
D.
Discussing over the telephone to gather feedback quickly from stakeholders
D.
Discussing over the telephone to gather feedback quickly from stakeholders
Answers
Suggested answer: C

In Lean Startup, what is based on the concept of ‘learn the most with the least effort’?

A.
A structured, timeboxed event
A.
A structured, timeboxed event
Answers
B.
A minimum viable product
B.
A minimum viable product
Answers
C.
A measurement of lead times
C.
A measurement of lead times
Answers
D.
A set of criteria to determine whether work can be started
D.
A set of criteria to determine whether work can be started
Answers
Suggested answer: B

Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?

A.
It should always be appropriate to the needs of the project
A.
It should always be appropriate to the needs of the project
Answers
B.
It should always be addressed during the daily stand-ups
B.
It should always be addressed during the daily stand-ups
Answers
C.
It should always be carried out formally
C.
It should always be carried out formally
Answers
D.
It should always be carried out informally
D.
It should always be carried out informally
Answers
Suggested answer: A

What BEST defines embryonic customer requirements?

A.
‘Fine-grained’ user stories
A.
‘Fine-grained’ user stories
Answers
B.
Epics
B.
Epics
Answers
C.
Sub-products
C.
Sub-products
Answers
D.
Technical stories
D.
Technical stories
Answers
Suggested answer: B

Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?

A.
PRINCE2 is predictive, but not emergent
A.
PRINCE2 is predictive, but not emergent
Answers
B.
PRINCE2 is predictive and can be emergent
B.
PRINCE2 is predictive and can be emergent
Answers
C.
PRINCE2 requires a lengthy start to a project
C.
PRINCE2 requires a lengthy start to a project
Answers
D.
PRINCE2 requires a disruptive start to a project
D.
PRINCE2 requires a disruptive start to a project
Answers
Suggested answer: B

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: A

Which statement about the waterfall methodology definition is CORRECT?

A.
It prevents earlier phases of development being revisited
A.
It prevents earlier phases of development being revisited
Answers
B.
It uses an iterative and incremental approach
B.
It uses an iterative and incremental approach
Answers
C.
It focuses on responding to changing requirements
C.
It focuses on responding to changing requirements
Answers
D.
It delivers products more frequently in shorter phases
D.
It delivers products more frequently in shorter phases
Answers
Suggested answer: A
Total 92 questions