Question 1

Report
Export
Collapse

Whose interests are specifically represented by the senior supplier?

Those ensuring the project is value for money.
Those ensuring the project is value for money.
Those who will use the project’s products.
Those who will use the project’s products.
Those who will be developing the project’s products.
Those who will be developing the project’s products.
Those responsible for the project’s technical integrity.
Those responsible for the project’s technical integrity.
1 and 2
1 and 2
2 and 3
2 and 3
3 and 4
3 and 4
1 and 4
1 and 4
Suggested answer: C

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_206&showNav=true&expandNav=true

asked 23/09/2024
Michał Wojciechowski
30 questions

Question 2

Report
Export
Collapse

Which is a key objective of running a workshop?

To make daily progress visible to the delivery team and key stakeholders
To make daily progress visible to the delivery team and key stakeholders
To encourage collaboration and create the defined outputs from the event
To encourage collaboration and create the defined outputs from the event
To communicate decisions to the wider stakeholder community
To communicate decisions to the wider stakeholder community
To make day-to-day decisions on behalf of the delivery team within a sprint
To make day-to-day decisions on behalf of the delivery team within a sprint
Suggested answer: B

Explanation:

Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_166&showNav=true&expandNav=true

asked 23/09/2024
Eduardo Messias Andrade e Oliveira
35 questions

Question 3

Report
Export
Collapse

Which statement about the waterfall methodology definition is CORRECT?

It states that deadlines should not be moved
It states that deadlines should not be moved
It has distinct goals for each stage of development
It has distinct goals for each stage of development
It is a behavior that involves making things transparent
It is a behavior that involves making things transparent
It promotes the use of experiments carried out in a scientific way
It promotes the use of experiments carried out in a scientific way
Suggested answer: B

Explanation:

Reference: https://www.lucidchart.com/blog/agile-vs-waterfall-vs-kanban-vs-scrum

asked 23/09/2024
Joshin Ogele
35 questions

Question 4

Report
Export
Collapse

How should product-based planning be used as part of PRINCE2 Agile?

To track progress against the team plan
To track progress against the team plan
To create the project plan using empiricism
To create the project plan using empiricism
To enable team planning to be predictive
To enable team planning to be predictive
To plan by focusing on the features required
To plan by focusing on the features required
Suggested answer: D

Explanation:

Reference: https://worldofagile.com/blog/product-based-planning-technique-in-prince2/

asked 23/09/2024
Mareah Allawi
31 questions

Question 5

Report
Export
Collapse

Which statement about the ‘directing a project’ process is CORRECT?

The project board should attend regular project progress meetings
The project board should attend regular project progress meetings
The project board should make decisions based on the Agilometer risks
The project board should make decisions based on the Agilometer risks
A project board member should fulfill the product owner role within a delivery team
A project board member should fulfill the product owner role within a delivery team
The project board should increase the stage-level time tolerance
The project board should increase the stage-level time tolerance
Suggested answer: C

Explanation:

Reference: https://www.prince2primer.com/directing-a-project-3/

asked 23/09/2024
Darren Bilmen
35 questions

Question 6

Report
Export
Collapse

Which TWO are the purposes of a highlight report?

To describe the MoSCoW priority of user stories.
To describe the MoSCoW priority of user stories.
To summarize the status of a work package.
To summarize the status of a work package.
To summarize the stage status.
To summarize the stage status.
To report any potential issues and risks
To report any potential issues and risks
1 and 2
1 and 2
2 and 3
2 and 3
3 and 4
3 and 4
1 and 4
1 and 4
Suggested answer: C

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_190&showNav=true&expandNav=true#:~:text=A%20highlight%20report%20is%20used,at%20intervals%20defined%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help

asked 23/09/2024
Kefash White
38 questions

Question 7

Report
Export
Collapse

To help with prioritization, what is MOST important when understanding the difference between scope and quality?

Combining functional and non-functional requirements
Combining functional and non-functional requirements
Creating non-functional requirements with user stories
Creating non-functional requirements with user stories
Differentiating functional from non-functional requirements
Differentiating functional from non-functional requirements
Defining non-functional requirements before functional requirements
Defining non-functional requirements before functional requirements
Suggested answer: C
asked 23/09/2024
muhammad ikram
32 questions

Question 8

Report
Export
Collapse

Why is Lean Startup included in the ‘starting up a project’ process in PRINCE2 Agile?

Because it explains how a small company can grow using traditional technologies
Because it explains how a small company can grow using traditional technologies
Because it is designed to manage projects, delivering products in timeboxes
Because it is designed to manage projects, delivering products in timeboxes
Because it enables agile to be used in challenging and uncertain situations
Because it enables agile to be used in challenging and uncertain situations
Because running a project and setting up a new business are the same
Because running a project and setting up a new business are the same
Suggested answer: C

Explanation:

Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_127&showNav=true&expandNav=true

asked 23/09/2024
Fthcx Fgghn
33 questions

Question 9

Report
Export
Collapse

Which process can take place during a release review workshop?

Controlling a stage
Controlling a stage
Managing product delivery
Managing product delivery
Managing a stage boundary
Managing a stage boundary
Directing a project
Directing a project
Suggested answer: B
asked 23/09/2024
Martin Stoyanov
50 questions

Question 10

Report
Export
Collapse

Which BEST describes the senior user role when tailoring the organization theme?

An ‘agile sponsor’
An ‘agile sponsor’
An ‘executive sponsor’
An ‘executive sponsor’
A ‘coach’
A ‘coach’
A ‘super product owner’
A ‘super product owner’
Suggested answer: D

Explanation:

Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_52

asked 23/09/2024
TAMPO DARKOI
40 questions
Total 92 questions
Go to page: of 10