List of questions
Related questions
Question 59 - PMI-RMP discussion
The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.
What should the project manager do?
A.
Implement the risk response strategies into the risk plan.
B.
Inform the sponsor that these risks should be added according to experience.
C.
Add the risks to the risk register and determine a contingency.
D.
Discuss and evaluate the identified risks with the project team.
Your answer:
0 comments
Sorted by
Leave a comment first