The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

A.

Implement the risk response strategies into the risk plan.

Answers
A.

Implement the risk response strategies into the risk plan.

B.

Inform the sponsor that these risks should be added according to experience.

Answers
B.

Inform the sponsor that these risks should be added according to experience.

C.

Add the risks to the risk register and determine a contingency.

Answers
C.

Add the risks to the risk register and determine a contingency.

D.

Discuss and evaluate the identified risks with the project team.

Answers
D.

Discuss and evaluate the identified risks with the project team.

Suggested answer: D

Explanation:

The project manager should discuss the identified risks with the project team to ensure that everyone is aware of the potential risks and can provide input on the likelihood and impact of each risk. This collaborative approach will help in developing a comprehensive risk management plan.

The project manager should discuss and evaluate the identified risks with the project team, as this is part of the risk identification process. The project manager can use their experience from previous projects to identify potential risks that may occur again on the new project, but they should also involve the project team to obtain their input and perspectives. The project team can help the project manager to validate, refine, and prioritize the identified risks, as well as to suggest possible risk responses. The project manager should document the identified risks and their characteristics in the risk register, which is a tool for risk management. The other options are not appropriate actions for the project manager to take. Implementing the risk response strategies into the risk plan is premature, as the project manager should first analyze and evaluate the risks before deciding on the best response strategies. Informing the sponsor that these risks should be added according to experience is not sufficient, as the project manager should also consult the project team and other stakeholders to ensure that all relevant risks are identified and assessed. Adding the risks to the risk register and determining a contingency is part of the risk analysis and response planning processes, which come after the risk identification process. The project manager should first discuss and evaluate the identified risks with the project team before moving to the next steps of risk management.Reference:2,3, [5]