ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 189 - PMI-RMP discussion

Report
Export

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

Answers
A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

Answers
B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

Answers
C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted.

Answers
D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted.

Suggested answer: D
asked 14/11/2024
Selladurai Ravi
42 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first