Question 190 - PMI-RMP discussion
An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource's availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.
What should the risk manager do next?
Update the risk register to indicate the risk has occurred and close out the expired risk from the register.
Update, continuously monitor, and communicate the residual and secondary risks of the backup resource on the project.
Hire a permanent developer to support the project, and work with the backup resource to eliminate this risk.
Hire another developer to support the project, contingent on when the experienced developer returns.