Question 6 - PMI-RMP discussion
A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.
What should the project manager have done differently?
A.
Executed the risk strategy response and recorded it in the risk register.
B.
Performed an analysis to affirm the request is valid before submitting.
C.
Informed the client and the project sponsor that the request is being submitted.
D.
Contacted the other stakeholders so they know the request is in process.