List of questions
Related questions
Question 57 - PMI-RMP discussion
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.
What should the project manager do first?
A.
Include the risk in the register and communicate with the stakeholders.
B.
Communicate with the client to provide the previous shutdown plan.
C.
Review and update the project schedule.
D.
Interview the other project manager to learn more details.
Your answer:
0 comments
Sorted by
Leave a comment first