Question 200 - PMI-RMP discussion
A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?
A.
Earned value management (EVM) variance metrics
B.
A risk burndown chart showing remaining risks
C.
The format established in the risk management plan
D.
An itemized list of remaining risks and their scores