ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers

Question list
Search
Search

List of questions

Search

Related questions











A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

How should the project manager work with these risk handling strategies?

A.

Review and revise the strategies periodically.

A.

Review and revise the strategies periodically.

Answers
B.

Implement the strategies after completing the risk analysis.

B.

Implement the strategies after completing the risk analysis.

Answers
C.

Implement the strategies immediately.

C.

Implement the strategies immediately.

Answers
D.

Ensure the strategies are approved by the stakeholders.

D.

Ensure the strategies are approved by the stakeholders.

Answers
Suggested answer: A

Explanation:

Risk handling strategies should be reviewed and revised periodically to ensure they remain effective and relevant as the project progresses. This allows the project manager to adapt to changing circumstances and minimize the impact of risks on the project.

According to the PMBOK Guide, risk handling strategies are the specific actions that are taken to implement the risk response plan. The risk response plan is the output of the Plan Risk Responses process, which describes how the project team intends to address the identified risks. The risk handling strategies should be aligned with the risk response strategies, which are the general approaches to deal with the risks, such as avoid, transfer, mitigate, accept, exploit, share, enhance, or accept.

The project manager should work with the risk handling strategies by reviewing and revising them periodically. This is because the project risks are not static, but dynamic and uncertain. They may change over time due to various factors, such as changes in the project scope, schedule, cost, quality, resources, stakeholder expectations, assumptions, constraints, etc. Therefore, the project manager should monitor and control the risk handling strategies to ensure that they are still effective and appropriate for the current risk situation. The project manager should also update the risk register and the risk report with the results of the risk handling strategies, such as the residual risks, secondary risks, and risk triggers.

The other options are not valid for how the project manager should work with the risk handling strategies:

Implement the strategies after completing the risk analysis: This is not a valid option because the risk analysis is not the final step in the risk management process. The risk analysis is part of the Perform Qualitative Risk Analysis and Perform Quantitative Risk Analysis processes, which come after the Identify Risks process and before the Plan Risk Responses process. The risk analysis helps the project manager to prioritize and evaluate the risks, but it does not provide the specific actions to address them. The risk handling strategies are developed in the Plan Risk Responses process, which comes after the risk analysis.

Implement the strategies immediately: This is not a valid option because the risk handling strategies should not be implemented without proper planning and approval. The risk handling strategies should be documented in the risk response plan, which should be communicated and approved by the project sponsor, customer, and other relevant stakeholders. The risk handling strategies should also be integrated with the other project management plans, such as the scope, schedule, cost, quality, resource, communication, procurement, and stakeholder management plans. The risk handling strategies should be implemented only when the risk triggers or conditions occur, or when the project manager decides to do so based on the risk analysis and evaluation.

Ensure the strategies are approved by the stakeholders: This is not a valid option because the approval of the risk handling strategies is not the only thing that the project manager should do with them. The approval of the risk handling strategies is part of the Plan Risk Responses process, which comes before the Implement Risk Responses and Monitor Risks processes. The project manager should also implement, monitor, and control the risk handling strategies to ensure that they are effective and appropriate for the current risk situation.

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

A.

Risk mitigation

A.

Risk mitigation

Answers
B.

Risk transfer

B.

Risk transfer

Answers
C.

Risk acceptance

C.

Risk acceptance

Answers
D.

Risk avoidance

D.

Risk avoidance

Answers
Suggested answer: B

Explanation:

By hiring a licensed contractor to complete the complex activity, the project manager is transferring the risk associated with that activity to the contractor. This is an example of risk transfer, as the responsibility for managing the risk is shifted from the project manager to the contractor.

According to the PMI Risk Management Professional (PMI-RMP) Handbook1, one of the domains of the PMI-RMP exam isRisk Response Planning, which involves developing options and actions to enhance opportunities and reduce threats to project objectives1.One of the strategies for negative risks or threats isrisk transfer, which involves shifting the impact of a threat to a third party, such as a contractor, a vendor, or an insurer2. In this situation, the project manager is performing risk transfer by hiring a licensed contractor to complete the work that is too complex to complete internally. By doing so, the project manager is transferring the responsibility and liability of the activity to the contractor, who is expected to have the expertise and resources to handle the complexity.The project manager is not performing risk mitigation, which involves reducing the probability and/or impact of a threat2.The project manager is not performing risk acceptance, which involves acknowledging the existence of a threat and making a conscious decision to accept it without taking any action2.The project manager is not performing risk avoidance, which involves changing the project plan to eliminate the threat or protect the project objectives from its impact2.Reference:1: PMI Risk Management Professional (PMI-RMP) Handbook, page 62: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 436.

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.

What should the team perform in this scenario?

A.

Quantitative risk analysis

A.

Quantitative risk analysis

Answers
B.

Risk response planning

B.

Risk response planning

Answers
C.

Monitor and control risks

C.

Monitor and control risks

Answers
D.

Risk urgency assessment

D.

Risk urgency assessment

Answers
Suggested answer: A

Explanation:

Quantitative risk analysis helps determine the minimum acceptable level of exposure and impact for each risk. It also helps to understand if the maximum level of exposure has been reached before escalating the risk. (Reference: PMBOK Guide, 6th Edition, p. 423)

The team should perform quantitative risk analysis, which is the process of numerically analyzing the effect of identified risks on overall project objectives. Quantitative risk analysis can help the team to establish the minimum acceptable level of exposure and impact for each risk, as well as the maximum level of exposure before escalation. Quantitative risk analysis can also provide probabilistic estimates of project outcomes, such as cost and schedule, and support risk prioritization and decision making.Reference:PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), Sixth Edition, 2017, p. 399; PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 69.

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

What should the risk manager do?

A.

Import a risk register from other industry chemical laboratories.

A.

Import a risk register from other industry chemical laboratories.

Answers
B.

Define chemical laboratory safety risk thresholds.

B.

Define chemical laboratory safety risk thresholds.

Answers
C.

Review published operational experience reports.

C.

Review published operational experience reports.

Answers
D.

Draft threat and opportunity risks that come to mind.

D.

Draft threat and opportunity risks that come to mind.

Answers
Suggested answer: C

Explanation:

Reviewing published operational experience reports from similar projects or industries can help the risk manager objectively identify risks for the chemical laboratory project. These reports provide valuable insights into potential risks and lessons learned from other projects.

According to the PMBOK Guide, one of the tools and techniques for the identify risks process isdata gathering. Data gathering is the process of collecting information from various sources to identify potential risks that may affect the project objectives. One of the data gathering techniques isdocument analysis, which involves reviewing and analyzing available project documents and other information sources to identify potential risks.Some of the documents that can be analyzed are project charter, project management plan, stakeholder register, assumptions log, agreements, and lessons learned1.

One of the information sources that can be useful for identifying risks in a project constructing a chemical laboratory ispublished operational experience reports. These are reports that document the experiences, lessons learned, best practices, and recommendations from other organizations or projects that have constructed or operated chemical laboratories. These reports can provide valuable insights into the common risks, challenges, and opportunities that are associated with chemical laboratory projects, such as safety hazards, environmental regulations, equipment failures, design specifications, quality standards, and stakeholder expectations.By reviewing published operational experience reports, the risk manager can objectively identify risks that are relevant and applicable to their project, as well as learn from the successes and failures of others23.

Some of the other options are not relevant or appropriate for the question scenario:

Importing a risk register from other industry chemical laboratories is not a valid option, as it would not allow the risk manager to objectively identify risks that are specific and unique to their project. A risk register is a document that records the identified risks, their causes, impacts, responses, owners, and other information related to the risk management process. A risk register is a project-specific document that reflects the characteristics, objectives, and context of a particular project. Importing a risk register from other industry chemical laboratories would not ensure that the risks are relevant, accurate, or comprehensive for the risk manager's project.Moreover, it would violate the intellectual property rights and confidentiality agreements of the other projects1.

Defining chemical laboratory safety risk thresholds is not a tool or technique for identifying risks, but rather for performing qualitative risk analysis. Risk thresholds are the measures of the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Risk thresholds are used to determine the significance of each risk and to prioritize them for further analysis or action.Defining chemical laboratory safety risk thresholds would not help the risk manager to objectively identify risks, but rather to evaluate them1.

Drafting threat and opportunity risks that come to mind is not an objective or systematic way of identifying risks, but rather a subjective and intuitive one. This option would rely on the risk manager's personal judgment, experience, or creativity, which may not be sufficient or reliable for identifying risks in a project constructing a chemical laboratory. This option would also not ensure that the risks are based on factual and verifiable information sources, such as project documents or published reports.Drafting threat and opportunity risks that come to mind would not help the risk manager to objectively identify risks, but rather to generate them1.

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget.

What should the project manager do next?

A.

Request a budget relief using the management reserve.

A.

Request a budget relief using the management reserve.

Answers
B.

Conduct a risk reassessment and reserve analysis.

B.

Conduct a risk reassessment and reserve analysis.

Answers
C.

Review the consequences of potential changes.

C.

Review the consequences of potential changes.

Answers
D.

Coach stakeholders on risk identification practices.

D.

Coach stakeholders on risk identification practices.

Answers
Suggested answer: B

Explanation:

The project manager should reassess the risks and analyze the reserve to determine if any adjustments can be made to accommodate the expected additional work. This will help in identifying potential budget-saving measures and making informed decisions on how to proceed.

According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, risk reassessment is the process of reanalyzing existing project risks and identifying new risks throughout the project life cycle1. Reserve analysis is the process of estimating the amount of contingency reserve and management reserve needed to account for the uncertainty and variability of the project2. In this case, the project manager should conduct a risk reassessment and reserve analysis as the next step, because the budget overruns during execution have changed the risk profile of the project and reduced the available funds to handle future risks. By conducting a risk reassessment, the project manager can update the risk register and the risk response plan with the current status of the project risks and the effectiveness of the risk responses. By conducting a reserve analysis, the project manager can determine if the remaining contingency reserve and management reserve are sufficient to cover the potential impact of the project risks, and request additional funds if needed.

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

A.

Executed the risk strategy response and recorded it in the risk register.

A.

Executed the risk strategy response and recorded it in the risk register.

Answers
B.

Performed an analysis to affirm the request is valid before submitting.

B.

Performed an analysis to affirm the request is valid before submitting.

Answers
C.

Informed the client and the project sponsor that the request is being submitted.

C.

Informed the client and the project sponsor that the request is being submitted.

Answers
D.

Contacted the other stakeholders so they know the request is in process.

D.

Contacted the other stakeholders so they know the request is in process.

Answers
Suggested answer: B

Explanation:

The project manager should have performed an analysis to ensure that the change request was valid and well-supported before submitting it to the sponsor. This would help in making a strong case for the change request and increase the chances of its approval.

The project manager should have performed an analysis to affirm the request is valid before submitting, as this would help to justify the need for the change and to demonstrate its impact on the project objectives, scope, schedule, cost, quality, and risk. The project manager should also have consulted with the project team, the subcontractor, and the risk owner to determine the best risk response strategy and to estimate the resources and time required for the change. By performing an analysis, the project manager could have increased the chances of getting the change request approved by the sponsor and avoided wasting time and effort on an invalid request.Reference:The Standard for Risk Management in Portfolios, Programs, and Projects, page 79; PMBOK Guide, 6th edition, page 115.

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

A.

Update the new risk in the risk register.

A.

Update the new risk in the risk register.

Answers
B.

Plan responses for the new risk.

B.

Plan responses for the new risk.

Answers
C.

Passively accept the new risk.

C.

Passively accept the new risk.

Answers
D.

Add the new risk to the watch list.

D.

Add the new risk to the watch list.

Answers
Suggested answer: A

Explanation:

The risk manager should first update the risk register with the new risk identified by the vendor. This will help in keeping track of all the risks associated with the project and facilitate the subsequent planning and management of the risks.

The risk manager should update the new risk in the risk register, which is a project document that records the details of all identified risks, including their description, category, cause, probability, impact, and response strategy. Updating the risk register is the first step to acknowledge the existence of the new risk and to document its characteristics and potential effects on the project objectives. The risk register can then be used as an input for the Plan Risk Responses process, where the risk manager can develop appropriate actions to address the new risk.Reference:PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), Sixth Edition, 2017, p. 397, 441.

During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?

A.

Contact the risk managers of the other projects and inform them

A.

Contact the risk managers of the other projects and inform them

Answers
B.

Include an escalation process in the risk management plan

B.

Include an escalation process in the risk management plan

Answers
C.

Take note of the extensive impact of these risks in the risk register

C.

Take note of the extensive impact of these risks in the risk register

Answers
D.

Address the unique characteristics of these risks on a case-by-case basis

D.

Address the unique characteristics of these risks on a case-by-case basis

Answers
Suggested answer: B

Explanation:

The risk manager should include an escalation process in the risk management plan to address risks that may impact other projects. This ensures that any identified risks that could affect multiple projects are communicated and managed appropriately across the organization.

The risk manager should include an escalation process in the risk management plan to deal with risks that may affect other projects or the organization as a whole. An escalation process is a set of procedures that defines how and when risks should be communicated to higher levels of authority or responsibility for decision making or resolution. The escalation process should specify the criteria, roles, responsibilities, and communication channels for escalating risks. The risk manager should follow the escalation process when identifying risks that may have extensive impacts beyond the scope of the project. The other options are not appropriate actions for the risk manager to take. Contacting the risk managers of the other projects and informing them is not sufficient, as it does not ensure that the risks are properly addressed or resolved. Taking note of the extensive impact of these risks in the risk register is not enough, as it does not involve the necessary stakeholders or decision makers. Addressing the unique characteristics of these risks on a case-by-case basis is not consistent, as it does not follow a standard process or protocol.Reference:2,3,4

A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.

What is an effect of adding the correlation to the model?

A.

Allows more risks to be included in the model.

A.

Allows more risks to be included in the model.

Answers
B.

Reduces the project completion duration.

B.

Reduces the project completion duration.

Answers
C.

Increases the standard deviation of the model.

C.

Increases the standard deviation of the model.

Answers
D.

Increases the probability of correlated activities finishing on time.

D.

Increases the probability of correlated activities finishing on time.

Answers
Suggested answer: C

Explanation:

Adding correlation to the model accounts for the relationship between activities, which can result in increased variability in the model's outcomes. This will increase the standard deviation, which is a measure of the uncertainty in the model.

According to the PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1, an effect of adding the correlation to the Monte Carlo schedule risk analysis model is that it increases the standard deviation of the model. This is because:

Correlation is the statistical relationship between two or more variables. In a schedule risk analysis, correlation can be used to model the dependency between the durations of different activities. For example, if two activities are positively correlated, it means that if one activity takes longer than expected, the other activity is also likely to take longer than expected. Conversely, if two activities are negatively correlated, it means that if one activity takes longer than expected, the other activity is likely to take shorter than expected.

A Monte Carlo schedule risk analysis is a simulation technique that uses random values for uncertain variables, such as activity durations, to generate possible outcomes for the project schedule. The simulation is repeated many times to produce a probability distribution of the project completion date and duration. The standard deviation is a measure of the variability or dispersion of the distribution. A higher standard deviation means that the distribution is more spread out and less predictable.

Adding correlation to the Monte Carlo schedule risk analysis model increases the standard deviation of the model because it introduces more variability and uncertainty to the simulation. Correlated activities can have a cumulative effect on the project schedule, either positively or negatively, depending on the direction and strength of the correlation. This can result in more extreme outcomes for the project completion date and duration, which increase the spread of the distribution and the standard deviation.

PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1

Risk Management Professional (PMI-RMP) Exam Cert Guide2

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X's project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X's project manager avoid this situation in the future?

A.

Prepare a contingency response plan to implement when delays occur

A.

Prepare a contingency response plan to implement when delays occur

Answers
B.

Ask the other project manager to officially confirm the new date in writing

B.

Ask the other project manager to officially confirm the new date in writing

Answers
C.

Request that the other project manager be added to relevant reports

C.

Request that the other project manager be added to relevant reports

Answers
D.

Request that the other project manager inform if any additional delays are expected

D.

Request that the other project manager inform if any additional delays are expected

Answers
Suggested answer: A

Explanation:

A contingency response plan helps the project manager to be prepared for unexpected situations, such as delays in equipment mobilization. This plan should outline alternative actions to take in case of such delays, minimizing the impact on the project.

According to the PMBOK Guide, a contingency response plan is a predefined action that the project team will take if an identified risk event occurs. It is part of the risk response plan, which is the output of the Plan Risk Responses process. The contingency response plan helps the project team to reduce the impact of the risk event on the project objectives, such as scope, schedule, cost, and quality. The contingency response plan should be documented in the risk register, along with the risk triggers, the assigned risk owners, and the allocated contingency reserves.

The project manager for project X should prepare a contingency response plan to avoid the situation of being dependent on the availability of critical equipment from another project, project Y. This is because the equipment mobilization is an external dependency, which is a type of inter-project dependency that occurs when a project relies on another project for a deliverable or resource. Inter-project dependencies are a source of risk for the project, as they may cause delays, conflicts, or changes in the project scope or quality. The project manager should identify, analyze, and monitor the inter-project dependencies, and plan appropriate risk responses to deal with them.

The contingency response plan for the equipment mobilization could include alternative sources of equipment, such as renting, purchasing, or borrowing from other projects or vendors. The contingency response plan could also include schedule adjustments, such as fast-tracking, crashing, or re-sequencing the activities that require the equipment. The contingency response plan should be implemented when the risk trigger occurs, such as the notification of the delay from the other project manager. The project manager should also communicate the contingency response plan to the relevant stakeholders, such as the project sponsor, customer, team members, and other project managers.

The other options are not valid for avoiding the situation in the future:

Ask the other project manager to officially confirm the new date in writing: This is not a valid option because it does not address the root cause of the problem, which is the dependency on the equipment from another project. Asking for a confirmation in writing may help to document the issue and track the progress, but it does not prevent the situation from happening again. The project manager should plan for the possibility of delays or changes in the equipment availability, and not rely on the other project manager's promises or commitments.

Request that the other project manager be added to relevant reports: This is not a valid option because it does not address the root cause of the problem, which is the dependency on the equipment from another project. Adding the other project manager to the relevant reports may help to improve the communication and coordination between the projects, but it does not prevent the situation from happening again. The project manager should plan for the possibility of delays or changes in the equipment availability, and not rely on the other project manager's information or updates.

Request that the other project manager inform if any additional delays are expected: This is not a valid option because it does not address the root cause of the problem, which is the dependency on the equipment from another project. Requesting the other project manager to inform if any additional delays are expected may help to anticipate and prepare for the impact, but it does not prevent the situation from happening again. The project manager should plan for the possibility of delays or changes in the equipment availability, and not rely on the other project manager's forecasts or estimates.

Total 201 questions
Go to page: of 21