PMI PMI-RMP Practice Test - Questions Answers, Page 5
List of questions
Related questions
A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.
Which type of analysis should the project manager use in this instance?
Check list analysis
Cause and effect
Specialized meeting
Quantitative analysis
A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.
What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)
Scope of work and requirements
Monte Carlo analysis from a similar project
List of pre-approved contractors
Organization chart for city permit department
Risk management plan
Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?
Exclude risk averse stakeholders from future risk discussions
Explain risk handling and mitigation strategies
Increase the impact of all risks in the risk breakdown structure (RBS)
Develop a generous probabilistic cash flow model
A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?
Each cause has a degree of uncertainty
Each cause has well defined owner
The causes represent actual conditions
The causes must be validated by the risk owner
The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.
The project manager would like the risk manager to take full advantage of opportunities.
Which response should the risk manager take?
Mitigate
Accept
Transfer
Exploit
The project manager performed' a variance analysis on the project during the execution phase. The variances were shown as increasing
What does this result imply?
The uncertainty and risk are increasing.
The project schedule is lagging behind.
There is no potential for future deviation.
The project is over budget.
The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.
What recommendation should the risk manager make to the project manager?
Add more float to the key activity
Add more contingency to the project
Review the plans for the key activity
Increase the budget for the key activity
A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.
What three artifacts should the project manager consult or review during this process? (Choose three.)
Project contracts
Lessons learned registers from analogous projects
Risk register
Risk management plan
Code of regulations
A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)
Applying modern risk management techniques.
Aligning to project constraints and priorities.
Ensuring risk response strategies mitigate all risks.
Minimizing implementation costs.
Obtaining stakeholder acceptance
Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?
Reduce the probabilities of those risks on the risk register
Transfer ownership of those risks to the customer
Implement the risk handling strategies for those risks
Request additional management reserve for those risks
Question