ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 3

Question list
Search
Search

List of questions

Search

Related questions











During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

A.

Reassess the design for the two pieces.

A.

Reassess the design for the two pieces.

Answers
B.

Escalate the situation and request approval to move forward.

B.

Escalate the situation and request approval to move forward.

Answers
C.

Confirm the results through a second pilot.

C.

Confirm the results through a second pilot.

Answers
D.

Update the assumptions log and assess the risk associated with it.

D.

Update the assumptions log and assess the risk associated with it.

Answers
Suggested answer: D

Explanation:

According to the PMBOK Guide, 6th edition, Section 11.2.1.2, Assumptions Log, an assumption is a factor that is considered to be true, real, or certain without proof or demonstration. Assumptions can affect the project planning and execution, and should be identified, documented, validated, and updated throughout the project life cycle. The assumptions log is an output of the Identify Risks process, and it records the project assumptions and their potential impact, validity, and priority. If the assumptions are found to be invalid or inaccurate, they may introduce new risks or change the existing risk exposure.Therefore, the project manager should update the assumptions log and assess the risk associated with the conflicting infrastructure pieces, and plan appropriate risk responses if needed.Reference: PMBOK Guide, 6th edition, Section 11.2.1.2, Assumptions Log

When conflicting infrastructure pieces are identified, the project manager should update the assumptions log to reflect the new information and assess the risks associated with the conflicting pieces. This allows the project manager to make informed decisions about how to address potential issues and avoid future problems. (Reference: Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, Section 11.3)

An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?

A.

Ensure sufficient resources are available

A.

Ensure sufficient resources are available

Answers
B.

Revise the risk management plan

B.

Revise the risk management plan

Answers
C.

Update the risk register

C.

Update the risk register

Answers
D.

Meet with the project's stakeholders

D.

Meet with the project's stakeholders

Answers
Suggested answer: B

Explanation:

The risk management plan is a document that describes how risk management activities will be structured and performed on a project.It defines the roles and responsibilities, risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms1.The risk management plan should be aligned with the project management plan, which defines the project scope, schedule, cost, quality, and other aspects2. When an organization decides to accelerate a key project, it means that the project objectives, assumptions, constraints, and environment have changed. This will affect the risk exposure and profile of the project, as well as the risk management approach and resources. Therefore, the first action for the project risk manager to take is to revise the risk management plan to reflect the new situation and ensure that the risk management process is still effective and efficient. Revising the risk management plan may involve updating the risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms to suit the accelerated project.The project risk manager should also communicate the revised risk management plan to the relevant stakeholders and obtain their approval and support1. Ensuring sufficient resources are available, updating the risk register, and meeting with the project's stakeholders are all important actions to take when accelerating a project, but they are not the first action. These actions should be done after revising the risk management plan, as they depend on the updated risk management approach and process.For example, the project risk manager may need to allocate more resources to risk management activities, identify and analyze new or changed risks, implement new or modified risk responses, and report the risk status and performance to the stakeholders based on the revised risk management plan1.Reference:2,1.

When a project is accelerated, the risk landscape changes. The project risk manager should first revise the risk management plan to address the new timeline and its potential impacts on the project. This will help in identifying new risks, reassessing existing risks, and updating risk responses.

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?

A.

Perform a sensitivity analysis to the higher-level aggregate activities

A.

Perform a sensitivity analysis to the higher-level aggregate activities

Answers
B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories

B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories

Answers
C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

Answers
D.

Perform a base line Monte Carlo simulation to address overall threats to project objectives

D.

Perform a base line Monte Carlo simulation to address overall threats to project objectives

Answers
Suggested answer: C

Explanation:

A SWOT analysis is a risk identification technique that helps to identify high-level and strategic project risks by examining the internal and external factors that may affect the project objectives. A SWOT analysis involves listing the strengths, weaknesses, opportunities, and threats of the project, and then analyzing how they may impact the project positively or negatively.A SWOT analysis can help to uncover potential risks that may not be obvious from other techniques, such as prompt lists, interviews, or brainstorming12

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment

What should the risk manager do?

A.

Confirm the risk triggers are still valid.

A.

Confirm the risk triggers are still valid.

Answers
B.

Ask the architect to develop acceptance criteria.

B.

Ask the architect to develop acceptance criteria.

Answers
C.

Review the feature with the project team.

C.

Review the feature with the project team.

Answers
D.

Escalate the issue to the project board.

D.

Escalate the issue to the project board.

Answers
Suggested answer: B

Explanation:

The risk manager should review the feature with the project team to determine the cause and impact of the untestability, and to identify possible solutions or alternatives. The risk manager should also update the risk register and the risk response plan accordingly. This is the best option among the given choices, as it involves the relevant stakeholders and follows the risk management process. Confirming the risk triggers are still valid is not sufficient, as it does not address the problem or its consequences. Asking the architect to develop acceptance criteria is not appropriate, as it may not be feasible or effective to test the feature with new criteria. Escalating the issue to the project board is premature, as it may not be necessary or desirable to involve the senior management without first analyzing the situation and proposing a course of action.Reference:PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition. Chapter 11: Project Risk Management, pp. 414-415. 5

When a key feature may not be testable due to changes in the environment, the risk manager should review the feature with the project team to understand the issue, assess its impact, and determine the appropriate risk response. This collaborative approach ensures that the team has a clear understanding of the situation and can work together to address the risk.

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

Answers
B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

Answers
C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

Answers
D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Answers
Suggested answer: D

Explanation:

According to the PMBOK Guide, 6th edition, Section 11.6.2.1, Sensitivity Analysis, a sensitivity analysis is a technique that helps to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes. A sensitivity analysis can be used to prioritize risks based on their relative effect on the project objectives, such as cost, schedule, quality, or scope. A sensitivity analysis can also help to identify areas where risk response efforts may be most effective.Therefore, the risk manager should perform a sensitivity analysis and determine the correct priority of every identified risk, rather than agreeing with the SME or the project sponsor, or marking every risk with the same or different priority without proper analysis.Reference: PMBOK Guide, 6th edition, Section 11.6.2.1, Sensitivity Analysis1

The risk manager should perform a sensitivity analysis to assess the impact of each risk on the project objectives. This will help in determining the correct priority of every identified risk, ensuring that resources are allocated effectively and that the most critical risks are addressed first.

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

A.

Use the Delphi technique involving experts who have identified opportunities in the past

A.

Use the Delphi technique involving experts who have identified opportunities in the past

Answers
B.

Interview more stakeholders who have a positive mindset

B.

Interview more stakeholders who have a positive mindset

Answers
C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

Answers
D.

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

D.

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

Answers
Suggested answer: B

Explanation:

The risk management plan is a document that describes how risk management activities will be structured and performed on a project.It defines the roles and responsibilities, risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms1.The risk management plan should be aligned with the project management plan, which defines the project scope, schedule, cost, quality, and other aspects2. When an organization decides to accelerate a key project, it means that the project objectives, assumptions, constraints, and environment have changed. This will affect the risk exposure and profile of the project, as well as the risk management approach and resources. Therefore, the first action for the project risk manager to take is to revise the risk management plan to reflect the new situation and ensure that the risk management process is still effective and efficient. Revising the risk management plan may involve updating the risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms to suit the accelerated project.The project risk manager should also communicate the revised risk management plan to the relevant stakeholders and obtain their approval and support1. Ensuring sufficient resources are available, updating the risk register, and meeting with the project's stakeholders are all important actions to take when accelerating a project, but they are not the first action. These actions should be done after revising the risk management plan, as they depend on the updated risk management approach and process.For example, the project risk manager may need to allocate more resources to risk management activities, identify and analyze new or changed risks, implement new or modified risk responses, and report the risk status and performance to the stakeholders based on the revised risk management plan1.Reference:2,1.

During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

A.

Utilize a Monte Carlo assessment to provide risk related impacts.

A.

Utilize a Monte Carlo assessment to provide risk related impacts.

Answers
B.

React to the secondary and residual risks only if they occur.

B.

React to the secondary and residual risks only if they occur.

Answers
C.

Include secondary and residual risks as part of the response.

C.

Include secondary and residual risks as part of the response.

Answers
D.

Transfer secondary and residual risks to the project sponsor.

D.

Transfer secondary and residual risks to the project sponsor.

Answers
Suggested answer: C

Explanation:

The The project manager should include secondary and residual risks as part of the risk response plan. Secondary risks are those risks that arise as a direct result of implementing a risk response to a specific risk. Residual risks are those risks that are expected to remain after the planned responses of risks have been taken, as well as those that have been deliberately accepted. Both secondary and residual risks should be identified, analyzed, and monitored throughout the project life cycle.The project manager should communicate the risk response plan to the project sponsor and other stakeholders, and explain how the project team has planned to manage the secondary and residual risks12

project manager should include secondary and residual risks in the risk response plan, as they may still impact the project. Proactively addressing these risks will help the project team to be prepared and manage them effectively if they occur.

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

A.

Industrial studies

A.

Industrial studies

Answers
B.

Commercial risk databases

B.

Commercial risk databases

Answers
C.

Organizational process assets (OPAs)

C.

Organizational process assets (OPAs)

Answers
D.

Enterprise environmental factors (EEFs)

D.

Enterprise environmental factors (EEFs)

Answers
Suggested answer: D

Explanation:

Enterprise environmental factors (EEFs) are conditions or circumstances that are not under the control of the project team, but may influence, constrain, or direct the project. EEFs include internal and external factors, such as organizational culture, market conditions, industry standards, government regulations, and academic research. In this case, the project manager should find the information about the new material from the research journal published by the local university, which is an example of an external EEF. This information may help the project manager to identify and analyze the risks associated with the new material and plan appropriate risk responses. Industrial studies, commercial risk databases, and organizational process assets (OPAs) are not the correct choices, as they are not relevant to the question. Industrial studies are systematic investigations of a specific industry or sector, which may provide general information about the market trends, opportunities, and challenges, but not specific information about the new material. Commercial risk databases are sources of information about historical or potential risks that may affect projects in different domains or regions, which may help the project manager to identify common or emerging risks, but not the risks related to the new material. OPAs are the plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization, which may help the project manager to follow the established guidelines and practices for risk management, but not to obtain new information about the new material.Reference:PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition. Chapter 2: The Environment in Which Projects Operate, pp. 38-39. 5

Enterprise environmental factors (EEFs) include information from external sources, such as academic research, industry studies, and market conditions. this case, the project manager should refer to the research journal published by the local university as an EEF to gather information about the new material and its associated risks.

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

A.

Risks that are tied to the success of the organization

A.

Risks that are tied to the success of the organization

Answers
B.

Risks as they apply to the organization's overall risk management philosophy and strategic ambition

B.

Risks as they apply to the organization's overall risk management philosophy and strategic ambition

Answers
C.

Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

C.

Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

Answers
D.

Risks related to cost that will impact the major projects that are currently in the execution phase

D.

Risks related to cost that will impact the major projects that are currently in the execution phase

Answers
E.

Risk mitigation actions that will require work from stakeholders

E.

Risk mitigation actions that will require work from stakeholders

Answers
Suggested answer: A, B

Explanation:

According to the PMBOK Guide, 6th edition, Section 11.1.3.1, Enterprise Environmental Factors, one of the factors that can influence the Plan Risk Management process is the organization's risk attitude, appetite, tolerance, and thresholds. These terms describe the degree of uncertainty that an organization is willing to accept in pursuit of its goals, and how it approaches, operates, and responds to risk. Therefore, when presenting their work to management, the risk manager should focus on the risks that are tied to the success of the organization, and the risks as they apply to the organization's overall risk management philosophy and strategic ambition. These aspects can help the management to understand the alignment of the project risks with the organizational objectives and values, and to make informed decisions about risk responses.The other options are less relevant or too specific for a management presentation, and may not reflect the organization's risk attitude or priorities.Reference: PMBOK Guide, 6th edition, Section 11.1.3.1, Enterprise Environmental Factors1

The risk manager should focus on risks that are directly tied to the success of the organization and those that align with the organization's risk management philosophy and strategic ambition. This will ensure that management is informed about the most relevant risks and opportunities for the project.

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

A.

Perform a FMECA fault tree analysis

A.

Perform a FMECA fault tree analysis

Answers
B.

Conduct a sensitivity analysis

B.

Conduct a sensitivity analysis

Answers
C.

Perform a decision tree analysis

C.

Perform a decision tree analysis

Answers
D.

Conduct an analytic hierarchy process

D.

Conduct an analytic hierarchy process

Answers
Suggested answer: C

Explanation:

A decision tree analysis is a tool that helps to evaluate and select the best option among different alternatives based on costs and probabilities. A decision tree analysis uses a graphical representation of a decision problem, where each node represents a decision point, a chance event, or an outcome. The branches of the tree show the possible choices, events, or consequences that can occur at each node. The end nodes of the tree show the expected value or payoff of each option, which is calculated by multiplying the probability and the cost or benefit of each outcome.A decision tree analysis can help to compare the expected values of different options and choose the one that maximizes the benefit or minimizes the cost1.A decision tree analysis can also help to incorporate uncertainty and risk into the decision making process, as it shows the range of possible outcomes and their likelihoods2. Therefore, the project manager should perform a decision tree analysis to evaluate and select the best option based on costs and probabilities for a mega facility development project. Performing a FMECA fault tree analysis, conducting a sensitivity analysis, or conducting an analytic hierarchy process are not the best options to evaluate and select the best option based on costs and probabilities. A FMECA fault tree analysis is a tool that helps to identify and analyze the potential causes and effects of failures in a system or process. It uses a graphical representation of a failure event, where each node represents a basic or intermediate event that contributes to the failure. The branches of the tree show the logical relationships between the events, using AND or OR gates.A FMECA fault tree analysis can help to calculate the probability and severity of failures, as well as to prioritize and mitigate the risks3. However, a FMECA fault tree analysis does not help to compare different options or alternatives, as it focuses on a single failure scenario. Conducting a sensitivity analysis is a tool that helps to measure how the uncertainty in the input variables of a model affects the output or outcome of the model. It uses a graphical or numerical representation of the relationship between the input and output variables, showing how the output changes when the input changes.A sensitivity analysis can help to identify the most critical or influential variables, as well as to test the robustness or reliability of the model4. However, a sensitivity analysis does not help to compare different options or alternatives, as it focuses on a single model or option. Conducting an analytic hierarchy process is a tool that helps to evaluate and select the best option among different alternatives based on multiple criteria. It uses a mathematical method of pairwise comparison, where each alternative is compared to each other in terms of each criterion. The results of the comparisons are then aggregated into a matrix, which shows the relative importance or preference of each alternative.An analytic hierarchy process can help to rank the alternatives and choose the one that best satisfies the criteria5.However, an analytic hierarchy process does not help to incorporate costs and probabilities into the decision making process, as it relies on subjective judgments and preferences.Reference:1,2,3,4,5.

A decision tree analysis is a quantitative risk analysis technique that helps evaluate and select the best option based on costs and probabilities. It visually represents different decision paths and their associated probabilities, allowing the project manager to compare and select the most appropriate option for the project.

Total 201 questions
Go to page: of 21