PMI PMI-RMP Practice Test - Questions Answers, Page 3
List of questions
Related questions
During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.
What action should the project manager take?
Reassess the design for the two pieces.
Escalate the situation and request approval to move forward.
Confirm the results through a second pilot.
Update the assumptions log and assess the risk associated with it.
An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?
Ensure sufficient resources are available
Revise the risk management plan
Update the risk register
Meet with the project's stakeholders
A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.
What should the risk management professional do next?
Perform a sensitivity analysis to the higher-level aggregate activities
Develop a risk breakdown structure (RBS) identifying the potential risk categories
Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis
Perform a base line Monte Carlo simulation to address overall threats to project objectives
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment
What should the risk manager do?
Confirm the risk triggers are still valid.
Ask the architect to develop acceptance criteria.
Review the feature with the project team.
Escalate the issue to the project board.
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.
What should the risk manager do?
Ask the project sponsor if every risk in the risk register can have the same priority.
Mark every identified risk as an extremely high priority and any future risks as a lower priority.
Agree with the SME, treat every risk with equal priority, and inform all stakeholders.
Perform a sensitivity analysis and determine the correct priority of every identified risk.
The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?
Use the Delphi technique involving experts who have identified opportunities in the past
Interview more stakeholders who have a positive mindset
Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis
Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis
During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?
Utilize a Monte Carlo assessment to provide risk related impacts.
React to the secondary and residual risks only if they occur.
Include secondary and residual risks as part of the response.
Transfer secondary and residual risks to the project sponsor.
A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.
Where should the project manager find this information?
Industrial studies
Commercial risk databases
Organizational process assets (OPAs)
Enterprise environmental factors (EEFs)
A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)
Risks that are tied to the success of the organization
Risks as they apply to the organization's overall risk management philosophy and strategic ambition
Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year
Risks related to cost that will impact the major projects that are currently in the execution phase
Risk mitigation actions that will require work from stakeholders
A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.
What should the project manager do to evaluate and select the best option based on costs and probabilities?
Perform a FMECA fault tree analysis
Conduct a sensitivity analysis
Perform a decision tree analysis
Conduct an analytic hierarchy process
Question