List of questions
Related questions
Question 10 - PMI-RMP discussion
The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X's project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.
How should project X's project manager avoid this situation in the future?
Prepare a contingency response plan to implement when delays occur
Ask the other project manager to officially confirm the new date in writing
Request that the other project manager be added to relevant reports
Request that the other project manager inform if any additional delays are expected
0 comments
Leave a comment first