Question 8 - PMI-RMP discussion
During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?
A.
Contact the risk managers of the other projects and inform them
B.
Include an escalation process in the risk management plan
C.
Take note of the extensive impact of these risks in the risk register
D.
Address the unique characteristics of these risks on a case-by-case basis
Your answer:
0 comments
Sorted by
Leave a comment first