List of questions
Related questions
Question 7 - PMI-RMP discussion
During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.
What should the risk manager do first?
A.
Update the new risk in the risk register.
B.
Plan responses for the new risk.
C.
Passively accept the new risk.
D.
Add the new risk to the watch list.
Your answer:
0 comments
Sorted by
Leave a comment first