ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 56 - PMI-RMP discussion

Report
Export

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

A.

Perform a qualitative risk analysis and update the results.

Answers
A.

Perform a qualitative risk analysis and update the results.

B.

Update the assumptions/exclusions register with the new information.

Answers
B.

Update the assumptions/exclusions register with the new information.

C.

Update the risk register and prepare for the Monte Carlo analysis.

Answers
C.

Update the risk register and prepare for the Monte Carlo analysis.

D.

Perform a quantitative risk analysis and update the results.

Answers
D.

Perform a quantitative risk analysis and update the results.

Suggested answer: C

Explanation:

The risk manager should perform a quantitative risk analysis to determine the potential impact of risks on the project's completion date. This will help in providing a more accurate project completion date to the customer, considering the risks and their potential effects on the project schedule.

According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain ofRisk Analysisis to perform quantitative risk analysis using techniques such as Monte Carlo simulation, decision tree analysis, sensitivity analysis, etc., to quantify the possible outcomes for the project and their probabilities, and to evaluate the cost and schedule impacts of risks1. In this scenario, the risk manager should perform a quantitative risk analysis and update the results, because the project costs have increased significantly and the customer has imposed a strict deadline for the project completion. A quantitative risk analysis will help the risk manager to estimate the probability of meeting the project objectives, such as cost and schedule, and to determine the appropriate contingency reserves for the project.A quantitative risk analysis will also provide more accurate and reliable information for the customer and the project team, and will support the risk response planning process2.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 92: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, pages 431-432.

asked 14/11/2024
Paul Beugelsdijk
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first