A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

A.

Scenario-based risk analysis

Answers
A.

Scenario-based risk analysis

B.

Quantitative risk analysis

Answers
B.

Quantitative risk analysis

C.

Qualitative risk analysis

Answers
C.

Qualitative risk analysis

D.

Monte Carlo analysis

Answers
D.

Monte Carlo analysis

Suggested answer: C