A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.
What type of request is the risk manager describing?
A.
A request to increase project earnings
B.
A request to increase project resources
C.
A challenge to stakeholder thresholds
D.
A challenge to the project investment