A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.

What type of request is the risk manager describing?

A.

A request to increase project earnings

Answers
A.

A request to increase project earnings

B.

A request to increase project resources

Answers
B.

A request to increase project resources

C.

A challenge to stakeholder thresholds

Answers
C.

A challenge to stakeholder thresholds

D.

A challenge to the project investment

Answers
D.

A challenge to the project investment

Suggested answer: C