ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 67 - PMI-RMP discussion

Report
Export

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

A.

Review the assumptions analysts

Answers
A.

Review the assumptions analysts

B.

Conduct a checklist analysis on each risk

Answers
B.

Conduct a checklist analysis on each risk

C.

Create a risk response plan for those risks

Answers
C.

Create a risk response plan for those risks

D.

Review the risk register to check for the new risks

Answers
D.

Review the risk register to check for the new risks

Suggested answer: D

Explanation:

If the project manager realizes that some risks have not been updated recently, they should review the risk register to check for new risks and ensure that all risks are accurately documented and updated.

The risk register is a document that contains information about the identified risks, their analysis, and their response plans. It is updated throughout the project life cycle as new risks emerge, existing risks change, or risks are closed. The project manager should review the risk register regularly to ensure that the project data is accurate and reflects the current risk situation. Reviewing the risk register also helps the project manager to identify any new risks that may have occurred since the last update, and to plan appropriate responses for them.Reference:PMI, Project Risk Management, 2nd edition, 2019, p.67-681

asked 14/11/2024
Ben Johnson
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first