Question 162 - PMI-RMP discussion
During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.
What should the risk manager do?
A.
Update the watchlist.
B.
Initiate a risk response when these risks occur.
C.
Address only the high-priority risk.
D.
Perform a risk urgency assessment.