There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.
What should the risk manager do to resolve this recurring situation?
A.
Review the stakeholders' risk appetite.
B.
Revisit the risk thresholds and triggers.
C.
Update the risk response strategies.
D.
Provide coaching to the risk action owners.