Question 181 - PMI-RMP discussion
A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.
What should the risk manager do in this case?
A.
Document the risk in the risk register for analysis.
B.
Document the detailed risk consequences,
C.
Immediately start the contracting process.
D.
Proceed with the quantitative risk analysis.