ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 181 - PMI-RMP discussion

Report
Export

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.

What should the risk manager do in this case?

A.

Document the risk in the risk register for analysis.

Answers
A.

Document the risk in the risk register for analysis.

B.

Document the detailed risk consequences,

Answers
B.

Document the detailed risk consequences,

C.

Immediately start the contracting process.

Answers
C.

Immediately start the contracting process.

D.

Proceed with the quantitative risk analysis.

Answers
D.

Proceed with the quantitative risk analysis.

Suggested answer: A
asked 14/11/2024
Gurdeep Girn
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first