ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 185 - PMI-RMP discussion

Report
Export

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

A.

Assess the risk register to ensure the secondary risks are realistic.

Answers
A.

Assess the risk register to ensure the secondary risks are realistic.

B.

Assess the impact of residual and secondary risks on project objectives.

Answers
B.

Assess the impact of residual and secondary risks on project objectives.

C.

Assess the change log to establish that changes were implemented.

Answers
C.

Assess the change log to establish that changes were implemented.

D.

Assess the stakeholder register to determine the impact of initial risks.

Answers
D.

Assess the stakeholder register to determine the impact of initial risks.

Suggested answer: B
asked 14/11/2024
bhaskar siddanadham
32 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first