Question 198 - PMI-RMP discussion
The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks.
What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?
A.
Stakeholder management and communication tools
B.
Team performance reports and analysis tools
C.
Schedule management tools (i.e., Gantt Charts)
D.
Estimation and probability analysis tools (i.e. Monte Carlo simulations)