Review the Version Report:

A.
The release date that has been added to this version should be reconsidered.
Answers
A.
The release date that has been added to this version should be reconsidered.
B.
More than 20 story points were burned when this chart was reviewed in July 2015.
Answers
B.
More than 20 story points were burned when this chart was reviewed in July 2015.
C.
Only three issues have been completed in the version, so a predicted end date is not possible.
Answers
C.
Only three issues have been completed in the version, so a predicted end date is not possible.
D.
The team should use time-based estimation, not story points.
Answers
D.
The team should use time-based estimation, not story points.
E.
There are too many unestimated issues in this version, so any predictions are inaccurate.
Answers
E.
There are too many unestimated issues in this version, so any predictions are inaccurate.
Suggested answer: B