A Scrum team working on multiple epics complains that they are constantly being pushed to complete more work than they think can be completed. Apparently, the product owner has constantly overloaded each of the past 8 sprints. Which single report can instantly prove their statement?

A.
Velocity Chart
Answers
A.
Velocity Chart
B.
Cumulative Flow Diagram
Answers
B.
Cumulative Flow Diagram
C.
Sprint Report
Answers
C.
Sprint Report
D.
Control Chart
Answers
D.
Control Chart
E.
Epic Burndown
Answers
E.
Epic Burndown
Suggested answer: A