Your team often accepts new requests from outside groups during an active sprint. You want to see if such frequent scope change mid-sprint is causing bottlenecks. Which report provides the needed insight?
A.
Control Chart
B.
Burndown Chart
C.
Average Age Chart
D.
Velocity Chart
E.
Cumulative Flow Diagram