You want to report on your team's performance to the stakeholders. View one of the reports for your team:

Based only on the report shown, which statement about your teams performance is definitely true?

A.
Your team is not estimating their work accurately.
Answers
A.
Your team is not estimating their work accurately.
B.
Your team sometimes commits more work than it can complete in an iteration.
Answers
B.
Your team sometimes commits more work than it can complete in an iteration.
C.
Your team is committing unestimated work to an iteration.
Answers
C.
Your team is committing unestimated work to an iteration.
D.
Scope change is affecting the team's ability to complete work on time.
Answers
D.
Scope change is affecting the team's ability to complete work on time.
E.
Your team is using sprint duration inconsistently
Answers
E.
Your team is using sprint duration inconsistently
Suggested answer: B

Explanation:

Based on the report shown, which is a Velocity Chart, the only statement that is definitely true about the team's performance is that they sometimes commit more work than they can complete in an iteration. This can be seen by comparing the green bars (completed work) and the gray bars (estimated work) in each sprint. For example, in Sprint 4, the team committed 10 story points but only completed 8 story points. The other statements are not necessarily true based on the report alone. For example, the team may be estimating their work accurately, but facing other challenges or impediments that prevent them from completing their work on time. Or, the team may not be committing unestimated work to an iteration, but rather re-estimating some issues during the sprint. Or, scope change may not be affecting the team's ability to complete work on time, but rather reflecting changes in priorities or requirements. Or, the team may be using sprint duration consistently, but varying the amount of work they commit to each sprint based on their capacity or velocity. For more information on how to interpret and use the Velocity Chart, seeVelocity Chart.Reference:Velocity Chart