Question 26 - BAP18 discussion
A Business Analyst is reviewing the stakeholder management strategy for a high profile I Human Resources (HR) protect.
Following an organizational restructure, Harvey's role has changed from Director of Operations to Director of HR and he has Inherited sponsorship of the project. Harvey was previously involved in the project, but had little interest because his focus was on the Operational Projects that he sponsored.
Which of the following sets of stakeholder management strategies represent appropriate approaches for Harvey; firstly for when the project started and secondly now that his role has changed?
A.
Keep watch; Constant active management
B.
Ignore; Constant active management
C.
Keep on side; Constant active management
D.
Ignore; Keep informed.
Your answer: