The Perform Integrated Change Control process occurs in which Process Group?

A.
Initiating
Answers
A.
Initiating
B.
Executing
Answers
B.
Executing
C.
Monitoring and Controlling
Answers
C.
Monitoring and Controlling
D.
Planning
Answers
D.
Planning
Suggested answer: C