Which input to the Plan Risk Management process provides information on high-level risks?

A.
Project charter
Answers
A.
Project charter
B.
Enterprise environmental factors
Answers
B.
Enterprise environmental factors
C.
Stakeholder register
Answers
C.
Stakeholder register
D.
Organizational process assets
Answers
D.
Organizational process assets