The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

A.
Work performance information.
Answers
A.
Work performance information.
B.
Inspections and audits.
Answers
B.
Inspections and audits.
C.
Payment systems.
Answers
C.
Payment systems.
D.
Procurement performance reviews.
Answers
D.
Procurement performance reviews.
Suggested answer: D