The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

A.
Project Communications Management
Answers
A.
Project Communications Management
B.
Project Integration Management
Answers
B.
Project Integration Management
C.
Project Risk Management
Answers
C.
Project Risk Management
D.
Project Scope Management
Answers
D.
Project Scope Management
Suggested answer: B