An output of the Plan Quality Management process is:

A.
A process improvement plan,
Answers
A.
A process improvement plan,
B.
Quality control measurements.
Answers
B.
Quality control measurements.
C.
Work performance information,
Answers
C.
Work performance information,
D.
The project management plan.
Answers
D.
The project management plan.
Suggested answer: A