A project manager should document the escalation path for unresolved project risks in the:

A.
Change control plan
Answers
A.
Change control plan
B.
Stakeholder register
Answers
B.
Stakeholder register
C.
Risk log
Answers
C.
Risk log
D.
Communications management plan
Answers
D.
Communications management plan
Suggested answer: D