Question 66 - CAPM discussion

Report
Export

Which process in Project Time Management includes reserve analysis as a tool or technique?

A.
Estimate Activity Resources
Answers
A.
Estimate Activity Resources
B.
Sequence Activities
Answers
B.
Sequence Activities
C.
Estimate Activity Durations
Answers
C.
Estimate Activity Durations
D.
Develop Schedule
Answers
D.
Develop Schedule
Suggested answer: C