The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

A.
Timing
Answers
A.
Timing
B.
Methodology
Answers
B.
Methodology
C.
Risk categories
Answers
C.
Risk categories
D.
Budgeting
Answers
D.
Budgeting
Suggested answer: A