When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

A.
Negative
Answers
A.
Negative
B.
Zero
Answers
B.
Zero
C.
Positive
Answers
C.
Positive
D.
Free
Answers
D.
Free
Suggested answer: C