Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

A.
Cost variance (CV)
Answers
A.
Cost variance (CV)
B.
Cost performance index (CPI)
Answers
B.
Cost performance index (CPI)
C.
Budget at completion (BAC)
Answers
C.
Budget at completion (BAC)
D.
Variance at completion (VAC)
Answers
D.
Variance at completion (VAC)
Suggested answer: B